Build-to-suit model: tenants control operations, so Compass's Scope 1/2 covers only corporate offices (~3,700 tCO2e). The real DC energy footprint sits in Scope 3 Category 13 — easy to misread as 'low-impact.'

What they do report

Design PUE1.25
WUE0 (waterless cooling)
Embodied carbon−33% per MW (2022-2024)

What they don't report

  • Scope 1/2 for data centers (only corporate offices reported)
  • Total capacity / campus count
  • Revenue

Why this matters

Companies building gigawatts of data center capacity without publishing environmental data are asking communities to approve projects on trust. If a developer won't disclose PUE, water consumption, and emissions before construction, that's a question for your planning board.