Glossary

Data-center vocabulary — what the terms actually mean

The jargon developers use in hearings and filings, translated into plain English. Every term links, so you can share /glossary#pue in a comment thread.

TermDefinition
PUEPower Usage Effectiveness — ratio of total facility energy to IT energy. Lower is better; hyperscalers target 1.10–1.20.
WUEWater Usage Effectiveness — liters of water per kWh of IT energy. Google fleet ~1.1 L/kWh; Meta claims 0.19.
CFECarbon-Free Energy — electricity from zero-carbon sources (solar, wind, nuclear, hydro). Distinct from RECs.
HyperscalerThe largest cloud/AI companies that build their own data centers at massive scale (Google, Microsoft, Amazon, Meta).
Colocation (colo)A data-center operator that leases space, power, and cooling to tenants — Equinix, Digital Realty, QTS, etc.
Interconnection queueThe list of projects waiting for grid connection approval from the regional operator (PJM, ERCOT, MISO, etc.).
MoratoriumA temporary ban or pause on new data-center construction, usually enacted by local or state government.
PPAPower Purchase Agreement — a long-term contract to buy electricity from a specific generator, often renewable.
Rack densityThe amount of power drawn per server rack, measured in kW. AI racks are 40–120+ kW vs. 5–15 kW traditional.
GPUGraphics Processing Unit — specialized chips (NVIDIA H100, B200) that power AI training and inference.
InferenceRunning a trained AI model to generate responses — what happens when you use ChatGPT, Gemini, etc.
TrainingThe initial process of building an AI model by processing massive datasets. Extremely energy-intensive.
Evaporative coolingCooling method that evaporates water to remove heat. Effective but water-intensive.
Liquid coolingPiping coolant directly to server chips. More efficient for high-density AI workloads.
Marginal emissionsThe CO₂ rate of the next power plant that would turn on to serve new load. The right signal for load-shifting.
Average emissionsThe fuel-mix intensity of the whole grid. Answers a different question from marginal — used for inventory accounting.
Location-based carbonCarbon accounting using the actual grid mix where energy is consumed. What a data center's real footprint looks like.
Market-based carbonCarbon accounting after applying PPAs and certificates. Can be a fraction of location-based intensity.
Large-load tariffA utility rate structure requiring very large customers to pay their own grid-upgrade costs, not socialize them onto ratepayers.
Capacity marketA market where utilities pay generators to be available on future peak days. Data-center demand is driving prices to record highs in PJM.
CBACommunity Benefits Agreement — a binding contract between a community and a developer setting terms like water caps, noise limits, and community payments.
Data dividendA community fund into which per-MW annual payments are placed, distributed or reinvested locally — modelled on Alaska's oil dividend.
ClawbackA contractual provision allowing tax abatements or incentives to be recovered if the developer fails to meet promised commitments.
Decommissioning bondA financial guarantee posted by the developer to cover site cleanup if the facility ceases operations.
ProfferIn Virginia land-use practice, a voluntary condition offered by a developer as part of a rezoning application. Should be recorded as binding.
Shell LLCA limited-liability company (often with a fanciful name) used by hyperscalers to acquire land and file permits without revealing the parent.
Certificate of Public Convenience and Necessity (CPCN)A regulatory approval a utility or generator must obtain before building. Some states exempt data-center backup power.
SubstationThe facility that steps voltage down (typically from 115–765 kV transmission to 12–34 kV distribution) at the edge of a data-center campus.
RTO / ISORegional Transmission Organization / Independent System Operator — the operators that run the wholesale grid (PJM, ERCOT, MISO, SPP, CAISO, NYISO, ISO-NE).
FERCThe Federal Energy Regulatory Commission — regulates interstate wholesale electricity and transmission. ERCOT is the notable exception (Texas-only).
EIA-930The U.S. Energy Information Administration's real-time grid demand and generation dataset. What the calculator's Live Grid mode uses.

Missing a term? Tell us and we'll add it. For the full technical background, see the Learn page.