Blog

233 GW of Demand Is Waiting in Line: Inside ERCOT's Data Center Queue

grid ERCOT Texas demand infrastructure

Texas's grid operator has 233 GW of large-load interconnection requests — roughly three times the state's current peak demand. Most of the queue is data centers. Here's what it means.

requestedscreenedstudiedagreementenergized INTERCONNECTION QUEUE

If you built every project currently sitting in ERCOT's large-load interconnection queue, you would need an electric grid three times the size of Texas's current one. That's not going to happen — but the queue tells a revealing story about where AI infrastructure investment is headed and what it's doing to the grid that serves 30 million Texans.

The numbers

As of ERCOT's March 2026 TAC report:

Metric Value
Total large-load requests 233 GW
Data-center share ~73% (~170 GW)
Requests with signed ISAs ~18 GW
Current ERCOT peak demand ~85 GW
Projected 2030 peak (ERCOT) ~115 GW

The queue is not a forecast — it's a wish list. Many projects will never break ground. Developers file early to secure their place in line, and attrition rates historically run 60–70%. But even if only a quarter materializes, that's a 50+ GW addition on a grid that struggled to keep the lights on during Winter Storm Uri.

Why Texas?

Three factors make Texas the epicenter of the data-center land rush:

  1. Deregulated market. ERCOT is the only major US grid that isn't federally regulated by FERC, which means faster interconnection timelines and fewer transmission cost-allocation disputes.

  2. Cheap land and power. West Texas wind and solar have pushed wholesale energy prices to some of the lowest in the nation — sometimes negative during sunny, windy afternoons. Developers can contract for renewable PPAs at $20–25/MWh.

  3. No state income tax. Combined with local Chapter 313 (now Chapter 403) property-tax abatements, the effective tax burden on a billion-dollar campus can be remarkably low.

The community tension

For small towns along the I-35 corridor and in the Permian Basin, the pitch is jobs and tax revenue. But the reality is more complicated:

  • A 200 MW data center employs 50–150 people once built. Construction crews are larger but temporary.
  • Property-tax abatements often run 10–20 years, meaning the school district and county see limited revenue during the period of highest community impact.
  • Water rights in West Texas are governed by the rule of capture — first come, first served — and data centers are arriving with deep pockets and drilling rigs.

Local water districts in Abilene and Midland have begun demanding long-term water-supply agreements before signing off on projects, a trend likely to spread.

What to watch

ERCOT's Board of Directors is considering a queue-management reform that would require refundable deposits and milestone deadlines to clear speculative filings. The April 2026 presentation to the Texas Senate Business & Commerce Committee signaled that legislators are paying attention.

Use the Data Centers tab to see the live ERCOT large-load queue data and the Officials tab to contact your Texas state legislators directly.

← PreviousThe Hidden Water Cost of Your AI Query: What the Data Actually Shows