Community briefing

The data center fight in Hazle Township, Pennsylvania

As of September 27, 2026, Hazle Township, Pennsylvania has a data center moratorium in force (action taken June 8, 2026; documented end date 2026-12-05).

Status is derived, not stored — a pause with a documented end date flips to Expired on its own — and the source is right next to the claim.

Status today

Enactedexpires 2026-12-05status
June 8, 2026action taken
Townshiplevel

180-day curative amendment pausing all data center applications; prompted by 1,300-acre Project Hazelnut proposal.

SourceNews
read 2026-09-11

An expiry date is the earliest a pause could have ended — extensions are common, so confirm with the clerk before citing it.

The project on the table

Project Hazelnut — In review

Operator: NorthPoint Development

Environmental permits under review at PA DEP (2 pending, 13 issued).

Next: Application filed. Ask the planning office for the hearing date and request formal notice.

Latest in the record

  • 2026-03-30 — WQM Major Sewage Treatment Plants application submitted to PA DEP under WPC State Water Pollution Control (4008405 / eFACTS auth 1564528) — DEP status: Issued. · source
  • 2026-03-30 — WQM Sewer Extensions application submitted to PA DEP under WPC State Water Pollution Control (4026402 / eFACTS auth 1564521) — DEP status: Issued. · source
  • 2026-03-24 — WQM Sewer Extensions application submitted to PA DEP under WPC State Water Pollution Control (4026401 / eFACTS auth 1563856) — DEP status: Issued. · source
  • 2026-02-20 — Water Obstruction & Encroachment Pmt application submitted to PA DEP under WRM Water Obstructions & Encroachments (E4002226-007 / eFACTS auth 1560084) — DEP status: Issued. · source
  • 2026-02-20 — Water Obstruction & Encroachment Pmt application submitted to PA DEP under WRM Water Obstructions & Encroachments (E4002226-008 / eFACTS auth 1560115) — DEP status: Issued. · source
  • 2025-11-12 — Chapter 102 Individual NPDES Permit application submitted to PA DEP under WPC Erosion & Sediment Control (PAD400107 / eFACTS auth 1548884) — DEP status: Issued. · source

Full dated timeline on the project tracker.

Source. Read 2026-09-20.

What to do next

Build a full action pack →

Nearby in Pennsylvania

All 19 tracked actions in Pennsylvania are on the state page.

As of August 2026 · changes weekly — re-check before citing

Illustrative rather than exhaustive — dozens of localities churn weekly, and this tracks the ones we have read a source for. **Each row carries its own provenance.** Rows showing a verification date link to the ordinance, the enacting body's own page, or a datable report of the vote, and were read on that date. Rows marked *unverified* came from bulk compilation and have not been checked against a primary source — the locality, the year, and the status may all be off. Verify one of those with the town clerk before citing it as precedent. **Expiry is derived, not asserted.** A row with a documented end date flips to *Expired* on its own once that date passes. A time-limited moratorium whose start date was never documented keeps showing as enacted — that is a known gap, not a claim that it is still in force. Moratoriums are also routinely extended, so an expiry date is the earliest it could have ended, not proof that it did.

Part of the U.S. data center moratorium tracker — open data, CC BY 4.0.

Toolkit States Tracker Search