Maine: data centers & your electric bill

The numbers residents cite at hearings — grid, water, and regulator contacts for Maine, from the free GridWatch toolkit.

Subscribe by RSS — moratorium changes and community headlines for Maine.

8tracked data center facilities
0.1 TWhestimated annual DC electricity
28.6¢residential rate per kWh
180grid gCO₂/kWh · water stress: low

As of July 2026 · changes over months · Source: U.S. Data Center Power Map by State — ElectricChoice.com compilation (updated July 2026; CC-BY 4.0). Underlying load research: LBNL 2024 US Data Center Energy Usage Report; rates: EIA

Facility counts vary by directory because each one draws the boundary differently — DataCenterMap lists 44 in Alabama where this table says 35, since it counts small network rooms alongside hyperscale campuses. Cite the TWh figure rather than the facility count when you can; it is the number that speaks to grid impact. Underlying load research is LBNL-2001637 (Dec 2024).

Your regulator

Maine Public Utilities Commissionwebsite · file a complaint

Official state energy data: EIA Maine electricity profile — generation, prices, and consumption from the U.S. Energy Information Administration.

Pushback already happening in Maine

WhereLevelStatusNoteSource
BangorLocalEnactedexpires soon — 2026-10-10180-day pause, 9-0. City cited lack of information about infrastructure impacts and no state-level framework to referenceSource
read 2026-08-13
Maine (statewide)StateVetoedLD 307 would have paused 20+ MW facilities to Nov 2027; governor vetoedSource
read 2026-08-04
SanfordLocalEnactedexpires 2027-01-3191-day emergency moratorium enacted May 19, 2026, halting a proposed Mousam River data center project; extended unanimously for 180 more days on Aug 5, 2026.Source
read 2026-08-12
EastportLocalEnactedMoratorium adopted unanimously targeting DeepGreen underwater data center proposalUnverified

As of August 2026 · changes weekly — re-check before citing

Illustrative rather than exhaustive — dozens of localities churn weekly, and this tracks the ones we have read a source for. **Each row carries its own provenance.** Rows showing a verification date link to the ordinance, the enacting body's own page, or a datable report of the vote, and were read on that date. Rows marked *unverified* came from bulk compilation and have not been checked against a primary source — the locality, the year, and the status may all be off. Verify one of those with the town clerk before citing it as precedent. **Expiry is derived, not asserted.** A row with a documented end date flips to *Expired* on its own once that date passes. A time-limited moratorium whose start date was never documented keeps showing as enacted — that is a known gap, not a claim that it is still in force. Moratoriums are also routinely extended, so an expiry date is the earliest it could have ended, not proof that it did.

Every data center already built in Maine

GridWatch does not yet track a named hyperscale campus in Maine, but that does not mean the state has none. DataCenterMap keeps a public directory of existing facilities — street addresses included — for Maine.

Browse the Maine directory →

Two caveats before you cite it at a hearing: it lists facilities that already exist, so a newly proposed campus will not appear; and it counts a small network room the same as a hyperscale campus, so the facility count is not a measure of power draw or community impact.

Latest Maine data center news

All Maine news → Live news search →

State municipal league: Maine Municipal Association