Community briefing

The data center fight in Starke County, Indiana

As of October 1, 2026, Starke County, Indiana has a data center moratorium in force (action taken Dec 15, 2025; documented end date 2026-12-15).

Status is derived, not stored — a pause with a documented end date flips to Expired on its own — and the source is right next to the claim.

Status today

Enactedexpires 2026-12-15status
Dec 15, 2025action taken
Locallevel

Board of Commissioners adopted Ordinance 2025-37 by a 3-0 vote on Dec 15, 2025, on the Plan Commission's Dec 4 favorable recommendation, barring building permits, improvement-location permits and site-plan applications for hyperscale data centers (>5,000 sq ft) in unincorporated Starke County for 12 months. Prompted by a Chicago-based firm's Nov 2025 inquiry about rezoning two parcels for a data center. No extension has been adopted. Instead the Plan Commission voted Aug 12, 2026 to send Resolution 2026-PC-15, a zoning amendment to define and prohibit commercial data centers, to a public hearing on Oct 14, 2026

SourceOfficial
read 2026-09-29

An expiry date is the earliest a pause could have ended — extensions are common, so confirm with the clerk before citing it.

The project on the table

Abei Energy data center proposal (rezoning request) — Blocked by ban

Operator: Abei Energy (data center division)

Chicago-based Abei Energy's data center division emailed the Starke County Plan Commission asking about rezoning two parcels from Agricultural to Industrial. County officials disclosed the inquiry to residents on 2025-11-03; Abei was placed on the Plan Commission's 2025-11-12 agenda. Exact parcels, acreage, and project size were never disclosed publicly. The county drafted a hyperscale data center moratorium ordinance in direct response and adopted it (Ordinance 2025-37) on 2025-12-15, before Abei's proposal advanced to a rezoning vote -- so this project's outcome is 'moratorium' (blocked by the county's own timeout), not a formal denial.

Next: Blocked by a local ban or moratorium - the project stopped at the ordinance, not at an application. Watch for the ordinance being challenged in court or allowed to lapse.

Latest in the record

  • 2026-07-15 — Plan Commission recommends a one-year extension of the data center moratorium; as of 2026-09 the Board of Commissioners has not been confirmed to have voted on it. · source
  • 2025-12-15 — Board of Commissioners adopts Ordinance 2025-37, a 12-month moratorium on permits for hyperscale (>5,000 sq ft) data centers in unincorporated Starke County, by a 3-0 vote. · source
  • 2025-12-04 — Starke County Plan Commission unanimously recommends a 12-month moratorium on hyperscale data center applications to the Board of Commissioners. · source
  • 2025-11-03 — Starke County commissioners publicly discuss Abei Energy's inquiry with citizens after incomplete email screenshots circulated on social media; Commissioner VanDeMark says a moratorium ordinance was already being drafted at the Plan Commission. · source

Full dated timeline on the project tracker.

Source. Read 2026-09-02.

Recent news

35 stories tracked since 2017-05-31 across 11 outlets. 22× A community is pushing back on a nearby data center. 11× Local officials are moving to pause or block the project. Most recent: “Starke County sheriff cites public opinion, data concerns for ending Flock contract” (WNDU, 2026-09-09).

+23 more on the story tracker.

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 35 headlines archived.

Where the decision gets made

Starke County Board of Commissioners — Zoning ordinance amendments and moratoria on building/site-plan permits for unincorporated Starke County, acting on recommendations from the Starke County Plan Commission

Meets: First Monday of each month at 5:00 PM CST; third Monday of each month at 9:30 AM CST
Where: 53 E Mound St, Knox, IN 46534

Public comment: Not specified on the commissioners' page; the county's data center moratorium was preceded by a noticed public hearing (see NOTICE OF PUBLIC HEARING, https://starke.in.gov/wp-content/uploads/2025/11/NOTICE-OF-PUBLIC-HEARING-Data-Center-Moratorium.pdf)

dbinkley@starke.in.gov · (574) 274-4853 · website

Meeting agendas →

Read from the official page on 2026-09-02. Meeting details change — confirm before you go.

Who votes on it

NameRoleEmailPhone Recorded stance
Mike VanDeMarkPresident, Board of Commissionersmike@plymouthfoundry.com574-274-4853Voted for Ordinance 2025-37 (12-month hyperscale data center moratorium), adopted 3-0 on 2025-12-15
Charles ChesakVice-President, Board of Commissionerscharlesrc2003@hotmail.com574-806-3746Voted for Ordinance 2025-37 (12-month hyperscale data center moratorium), adopted 3-0 on 2025-12-15
Don BinkleyMember, Board of Commissionersdbinkley@starke.in.gov574-249-0895Voted for Ordinance 2025-37 (12-month hyperscale data center moratorium), adopted 3-0 on 2025-12-15
Bill R. Crase, Jr.President, County Councilbill_crase@live.com574-249-8809not recorded
Dave PearmanVice-President, County Councilstarkecouncild3@aol.com574-249-0519not recorded
Todd LeinbachMember, County Counciltleinbach@starke.in.gov574-249-5030not recorded
Howard BaileyMember, County Councilhabjr13@gmail.com574-806-8050not recorded
Bruce BennettMember, County Councilnbbennettfarm@gmail.com574-806-2408not recorded
Kay GudemanMember, County Councillexusdiana1953@gmail.com574-806-1078not recorded
Cassandra HineMember, County Councilcassi46534@gmail.com574-249-8943not recorded

From the locality's own roster page; "not recorded" means no public statement is on file, not neutrality.

What to do next

Build a full action pack →

Nearby in Indiana

All 23 tracked actions in Indiana are on the state page.

As of August 2026 (2m ago) · changes weekly — re-check before citing

Illustrative rather than exhaustive — dozens of localities churn weekly, and this tracks the ones we have read a source for. **Each row carries its own provenance.** Rows showing a verification date link to the ordinance, the enacting body's own page, or a datable report of the vote, and were read on that date. Rows marked *unverified* came from bulk compilation and have not been checked against a primary source — the locality, the year, and the status may all be off. Verify one of those with the town clerk before citing it as precedent. **Expiry is derived, not asserted.** A row with a documented end date flips to *Expired* on its own once that date passes. A time-limited moratorium whose start date was never documented keeps showing as enacted — that is a known gap, not a claim that it is still in force. Moratoriums are also routinely extended, so an expiry date is the earliest it could have ended, not proof that it did.

Part of the U.S. data center moratorium tracker — open data, CC BY 4.0.