Bradenton Crossings Data Center Withdrawn
35-acre mixed development at 202 13th Ave E; data-center piece withdrawn July 2026. The withdrawal plus utility-strain concerns prompted county commissioners to draft a countywide data center moratorium ordinance.
Key facts
- Size
- 35 ac
- Location
- Bradenton (Manatee County), Florida
- Stage today
- Withdrawn
What to do next
Next step: Withdrawn — confirm it is dead in the record and watch for the same site resurfacing under a new name or LLC.
What has happened so far (6 events)
- 2025-10-01filing
A submission for the Bradenton Crossings development (a 35.28-acre site at 202 13th Ave. E. in Bradenton) included a data center component as part of the project application. · source - 2026-06-16public-comment
Residents urged Manatee County commissioners to proactively investigate and regulate data center development before any project is formally proposed. · source - 2026-07-16withdrawal
The developer withdrew the data center component from the Bradenton Crossings project application amid mounting regulatory scrutiny in the region. · source - 2026-07-21coverage
The Bradenton Journal reported Manatee County was poised to consider a 12-month moratorium on new data centers to give the county time to develop rules protecting water supply and infrastructure. · source - 2026-07-28vote
Manatee County commissioners voted unanimously to direct staff to draft an ordinance imposing a temporary moratorium on data center and other large-load utility applications, citing water and electrical grid strain. · source - 2026-08-04environmental
WUSF reported that residents cited severe drought conditions in West Manatee and insufficient water supply as reasons to pause data center development, noting such facilities can use up to 5 million gallons of water daily. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Florida DEP — Division of Air Resource ManagementThe program page: which permits this state requires, and the office that issues them.
- DEP Nexus electronic documentsSearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Bradenton (Manatee County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Bradenton (Manatee County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Florida Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Manatee County community briefing — Enactedterm not documented
- Florida briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Florida
- Fort Meade Data Center Campus — Fort Meade (Polk County) Approved
- Project Tango — Loxahatchee (Palm Beach County) Denied
- Sarasota County Data Center (Cattleman Road) — Sarasota County In review
Cite this page: GridWatch AI, “Bradenton Crossings Data Center”, aigridwatch.com/projects/bradenton-crossings-fl, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.