CoreWeave Muskogee OK
Data center by CoreWeave in Muskogee, Oklahoma. Operating.
Key facts
- Operator
- CoreWeave
- Owner
- CoreWeave
- Tenant
- OpenAI
- Location
- Muskogee, Oklahoma
- Stage today
Source
read 2026-08-14
What to do next
Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.
What has happened so far (6 events)
- 2024-06-06financing
Core Scientific signs initial 200 MW, 12-year hosting contract with CoreWeave valued at over $3.5 billion in cumulative revenue; no specific sites named but this is the master contract the Muskogee facility later falls under. · source - 2024-07-05financing
Core Scientific announces a second 70 MW CoreWeave hosting agreement, bringing the total to 270 MW across two 12-year contracts worth approximately $4.7 billion in cumulative revenue. · source - 2024-10-22financing
CoreWeave exercises its final contract option for approximately 120 MW of additional critical IT load, bringing the total Core Scientific-CoreWeave commitment to approximately 500 MW across six sites with $8.7 billion in total potential revenue over 12 years. · source - 2024-11-18construction
Core Scientific and Port Muskogee break ground on a 100 MW HPC data center (70 MW for NVIDIA GPU computing load, 30 MW ancillary), part of the 500 MW CoreWeave contract; projected to generate $182 million in net local economic benefits, support 150 jobs, and bring over $12 million in property and sales taxes to local institutions; expected operational in 2026. · source - 2026-05-06announcement
Core Scientific announces plans to expand its Muskogee campus to approximately 1.5 GW of gross power (1.0 GW leasable) through an agreement to acquire Polaris DS LLC and its 440 MW of grid-connected power under Oklahoma Gas & Electric service agreements, plus 250 acres secured for expansion; the first 70 MW building targets Q2 2026 delivery with NVIDIA GB300 platform, and a second 82.5 MW building targets Q4 2027. · source - 2026-08-14operational
Core Scientific completes acquisition of Polaris DS LLC for approximately $444 million in cash, securing roughly 440 MW of grid-connected power capacity under existing Oklahoma Gas & Electric service agreements to advance the planned 1.5 GW Muskogee campus expansion; next 82 MW building expected to reach customers in the second half of 2027. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Oklahoma DEQ — Air Quality DivisionThe program page: which permits this state requires, and the office that issues them.
- Search Oklahoma DEQ — Air Quality Division for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Muskogee planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Muskogee property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- Southwest Power Pool (Plains) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Oklahoma Corporation Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 35.720, -95.390 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Oklahoma briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Oklahoma
- Google Pryor (North) — Pryor, 41 mi
Cite this page: GridWatch AI, “CoreWeave Muskogee OK”, aigridwatch.com/projects/coreweave-muskogee-ok, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).