Google West Memphis In review
$4B, 1,178-acre campus with 5 buildings in West Memphis, Arkansas. Under construction.
Key facts
- Operator
- Owner
- Size
- 1,178 ac
- Location
- West Memphis, Arkansas
- Stage today
- In review
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (14 events)
- 2024-11-01filing
Groot LLC, a Google-linked entity, paid $16.5 million to buy roughly 1,117 acres of agricultural land on Bollinger Road in West Memphis, Crittenden County. · source - 2025-05-15vote
West Memphis City Council unanimously approved a MOU, development agreement, and PILOT incentive package with Groot LLC for a project valued at up to $10 billion, with potential for up to $50 billion in personal-property tax abatements over 30 years. · source - 2025-09-01filing
Entergy Arkansas and Google jointly sought Arkansas Public Service Commission approval of a special electricity rate contract to power the West Memphis data center. · source - 2025-09-05coverage
Reporting confirmed Google (via Groot LLC) as the company behind the planned $10 billion, five-building data center campus on 1,178 acres south of Bollinger Road, dubbed Project Pyramid. · source - 2025-10-02announcement
Google, Governor Sarah Sanders, and state/local officials formally announced a $4 billion AI/cloud data center project in West Memphis — Google first data center in Arkansas — with a $25 million Energy Impact Fund for low-income households in Crittenden County. · source - 2025-10-02utility
Entergy Arkansas announced it would power the Google project with a 600 MW Cypress Solar project and 350 MW of battery storage, with Google saying the deal would deliver over $1.1 billion in net benefits to Entergy customers. · source - 2025-11-17hearing
Arkansas PSC held a hearing on the special rate contract between Entergy and Google; the public was asked to leave during portions covering confidential contract details, drawing transparency criticism. · source - 2025-12-05ruling
Arkansas PSC approved Entergy special rate contract with Google but denied the utility requested ratemaking treatment and deferred a decision on investment tax credit treatment for the Cypress Solar facility. · source - 2025-12-12coverage
Arkansas Advocate reported state officials were largely declining to scrutinize fiscal and environmental tradeoffs of the data center boom out of fear of losing investment to other states. · source - 2026-01-01ruling
Arkansas PSC issued a follow-up order reversing itself to allow investment tax credits from the Cypress Solar facility to be used in pricing under the Google contract. · source - 2026-02-26coverage
Google began actively hiring for electrical engineer and facilities technician roles at the West Memphis data center, which remained under construction with an expected 18-24 month build timeline. · source - 2026-05-03coverage
Reporting revealed Google and Entergy were keeping the full terms of their energy rate contract sealed/confidential, raising transparency concerns among ratepayer advocates. · source - 2026-06-04financing
Reporting detailed that bond issuances tied to the West Memphis Google data center PILOT financing could total as much as $60 billion in permanent financing authority over the deal 30-year term. · source - 2026-07-29public-comment
At an Arkansas PSC hearing on Entergy proposed residential rate increase, speakers including the Little Rock NAACP chapter head cited the sealed Google contract as evidence of a lack of transparency. · source
Find the paper trail
Find the paper trail (0 filed · 12 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Arkansas DEQ — Office of Air QualityThe program page: which permits this state requires, and the office that issues them.
- ADEQ Permit Data SystemSearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search West Memphis planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search West Memphis property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- MISO (Midwest & Gulf) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Southwest Power Pool (Plains) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Arkansas Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Arkansas briefing — rates, grid carbon, PUC contacts.
Cite this page: GridWatch AI, “Google West Memphis”, aigridwatch.com/projects/google-west-memphis-ar, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.