Project dossier · Monroe Township (Gloucester County), New Jersey

Hexa Builders data center (Black Horse Pike) In review

Previously-approved warehouse project at 3043 South Black Horse Pike amended in early April 2026 to include a 1,000,000 sq ft data center. Two weeks later the township council stripped data-center permissions from the site and banned data centers township-wide; the planning board then deemed the amended application incomplete. Hexa is now suing the township for $300M+. Not dead - the litigation decides it.

Key facts

Filing LLC
Hexa Builders LLC
Location
Monroe Township (Gloucester County), New Jersey
Application filed
2026-04-01
Stage today
In review

Source
read 2026-08-07

What to do next

Next step: Application filed. Ask the planning office for the hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (30 events)

  • 2019-09-23rezoning
    Monroe Township Council adopted Resolution R:221-2019, declaring the Commercial Corridor Rehabilitation Area along Black Horse Pike (Block 8401, Lots 8, 9, and 10, approximately 158 acres) an area in need of redevelopment. · source
  • 2023-02-01rezoning
    Monroe Township adopted Ordinance O:04-2023, approving the Hexa Builders Redevelopment Plan (revised November 15, 2022) permitting warehouse, storage, and distribution uses on the 158-acre site; data centers were not included as a permitted use. · source
  • 2023-03-16hearing
    The New Jersey Pinelands Commission published a public notice and scheduled a hearing on Monroe Township Ordinance O:04-2023 to determine whether the Hexa Builders Redevelopment Plan conformed with the Pinelands Comprehensive Management Plan. · source
  • 2025-03-12rezoning
    Monroe Township Council adopted Ordinance O:02-2025, amending the Hexa Builders Redevelopment Plan to add data centers and associated infrastructure (electrical systems, cooling equipment, network infrastructure, emissions control) as a permitted use. · source
  • 2025-12-23filing
    Residents within 200 feet of the Hexa Builders redevelopment site received certified mail notice of a January 8, 2026 planning board meeting regarding a 1.6-million-square-foot warehouse proposal at 3043 South Black Horse Pike. · source
  • 2026-01-08meeting
    At a January 8 Monroe Planning Board meeting, residents objected to the data center proposal, but the board approved Hexa's project that evening. · source
  • 2026-01-28vote
    On January 28 the Monroe Township Council directed the planning board to develop stricter data center standards, citing resident opposition. · source
  • 2026-02-02ruling
    On February 2 the Monroe Planning Board memorialized its approval of Hexa's project in a written resolution. · source
  • 2026-03-11meeting
    More than 100 residents packed a Monroe Township Council meeting lasting five hours; environmental groups including CRAN, Sustain South Jersey, Pinelands Alliance, and Food and Water Watch attended and raised concerns about the data center's water, energy, and noise impacts. · source
  • 2026-03-16announcement
    Mayor Gregory Wolfe announced in a Facebook video that a data center would not be coming to Monroe Township and that the council would remove data centers as a permitted use from the Hexa Redevelopment Plan at the March 25 meeting. · source
  • 2026-03-25vote
    At a March 25 council meeting, Monroe Township leaders heard resident concerns and approved a motion to change the ordinance so data centers could not be built in the community. · source
  • 2026-03-25filing
    Council introduced Ordinance O:20-2026 to eliminate data center use from the Hexa Builders Redevelopment Plan; all council members except John Valentine voted to introduce it, with Valentine wanting a broader ban and better public notification instead. · source
  • 2026-04-01filing
    Hexa Builders filed an amended application in early April 2026 converting one approved warehouse into a 1M sq ft data center at 3043 South Black Horse Pike. · source
  • 2026-04-08vote
    The Monroe Township council and ordinance committee voted to introduce a separate township-wide data center ban ordinance, with a final adoption vote scheduled for April 22. · source
  • 2026-04-22vote
    Township council passed two ordinances: one stripping data-center permissions from the specific site, the other banning data centers township-wide. · source
  • 2026-05-08coverage
    CBS Philadelphia reported on the ban, quoting Mayor Wolfe stating that Monroe Township has now banned any data center use from ever coming to the township. · source
  • 2026-05-12meeting
    Planning board unanimously deemed the amended site-plan application incomplete - blocking the project without rejecting it on the merits. · source
  • 2026-05-12ruling
    At the completeness review, township planner Christopher Dochney cited multiple application deficiencies including a missing environmental assessment, no Pinelands Certificate of Filing, unsigned plans, absent stormwater maintenance schedule, and incomplete electrical infrastructure documentation covering 3+ acres. · source
  • 2026-05-13operational
    Monroe Township's data center ban officially took effect on May 13. · source
  • 2026-05-13public-comment
    A coalition of 60 environmental, labor, and community organizations sent a letter to Governor Sherrill urging her to use emergency powers to impose a statewide moratorium on data centers consuming 20+ megawatts; Monroe Township resident Aleasha Whipple was quoted as a local organizer. · source
  • 2026-05-22hearing
    On May 22 Hexa presented its still-pending application, including the data center component, at a packed special planning board meeting attended by opposed residents. · source
  • 2026-06-05lawsuit
    On June 5 Hexa Builders filed a 104-page, 20-count lawsuit in New Jersey Superior Court alleging First and 14th Amendment and state-law violations and seeking $300 million after Monroe denied its application. · source
  • 2026-07-06filing
    On July 6 the case was moved from New Jersey Superior Court to federal court in Camden; the Superior Court case closed. · source
  • 2026-07-09meeting
    At a July 9 planning board session, resident John Romano questioned how Hexa's application advanced and raised concerns about potential noise and pollution impacts on his property. · source
  • 2026-07-14hearing
    A case management conference was held in the Hexa Builders LLC and 3043 Williamstown Urban Renewal LLC v. Monroe Township case (Docket No. GLO-L-805-26). · source
  • 2026-07-17coverage
    Township Solicitor Sandra Graise stated the municipality is committed to vigorously and zealously defending the lawsuit while protecting residents' interests. · source
  • 2026-07-28filing
    On July 28 Monroe attorney Todd Gelfand filed a four-page letter seeking dismissal, arguing the ban does not regulate the content of speech, a speaker, a message, or the plaintiffs' ability to engage in expressive activity. · source
  • 2026-07-30ruling
    Hexa Builders sued Monroe Township for more than $300 million in damages over the ban and the completeness review. · source
  • 2026-08-01filing
    On August 1 Hexa's attorney Jim Maley asked the federal judge to reject Monroe Township's request to dismiss the lawsuit. · source
  • 2026-08-03filing
    Hexa attorney Jim Maley filed a letter requesting remand of the non-constitutional state-law claims back to New Jersey Superior Court, arguing state courts have more expertise on local land use laws. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

  • New Jersey DEPThe program page: which permits this state requires, and the office that issues them.
  • NJDEP DataMinerSearchable public filings — search the operator, the shell LLC on the deed, and the address.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 39.680, -74.990 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Recent news

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 3 headlines archived.

Around here

Other tracked projects in New Jersey

Cite this page: GridWatch AI, “Hexa Builders data center (Black Horse Pike)”, aigridwatch.com/projects/hexa-monroe-township-nj, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).