Microsoft Goodyear
Chip types: H100,B200. Epoch AI estimates ~202 MW.
Key facts
- Operator
- Microsoft
- Owner
- Microsoft
- Tenant
- OpenAI, Microsoft
- Size
- 202 MW
- Location
- Goodyear, Arizona
- Stage today
Source
read 2026-08-14
What to do next
Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.
What has happened so far (7 events)
- 2018-08-01financing
Microsoft purchased 279 acres in Goodyear from Carefree Partners Investments for $48 million, land later used for its data center campus south of I-10 and Phoenix Goodyear Airport. · source - 2018-12-01rezoning
Goodyear City Council approved rezoning of Microsoft's parcel from final planned area development to I-1 (light industrial park) with a PAD overlay (December 2018). · source - 2019-03-01permit
Goodyear City Council approved a site plan and an expedited self-certification construction process for Microsoft's project (March 2019). · source - 2019-05-02announcement
Microsoft publicly revealed its Goodyear data center plans, having also acquired an additional 147 acres from DRI FR Goodyear LLC for $37 million at Citrus and Indian School roads. · source - 2021-06-15operational
The first of Microsoft's three planned West Valley (Arizona) data centers, part of the West US 3 Azure region anchored by El Mirage and Goodyear campuses, went online. · source - 2023-03-06vote
Goodyear City Council unanimously approved an amended development agreement requiring Microsoft's fourth and fifth buildings to use air cooling instead of direct evaporative cooling, with Microsoft committing $36 million toward a $90 million expansion of the 157th Avenue Wastewater Treatment Plant, a $5 million financial-assurance deposit for a new sewer line, and $800,000 for a city coordinator position. · source - 2026-06-09financing
Microsoft paid $130 million for an additional 100-acre development site in Goodyear, about 27 miles west of Phoenix. · source
Find the paper trail
Find the paper trail (1 filed · 11 places to look)
Permits already on file (1)
Filings we have a source for — the record, not a place to look for one.
- 2019-03-01
Goodyear City Council approved a site plan and an expedited self-certification construction process for Microsoft's project (March 2019). · source
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Arizona DEQ — Air Quality DivisionThe program page: which permits this state requires, and the office that issues them.
- Search Arizona DEQ — Air Quality Division for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Goodyear planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Goodyear property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Arizona Corporation Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 33.420, -112.360 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Arizona briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Arizona
- Stream Phoenix — Goodyear, 0 mi
- Google Mesa — Mesa, 31 mi
- La Osa — Pinal County (near Eloy), 66 mi Awaiting decision
Cite this page: GridWatch AI, “Microsoft Goodyear”, aigridwatch.com/projects/microsoft-goodyear, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).