Project dossier · South Whitehall Township (Lehigh County), Pennsylvania

Project Atlas In review

Environmental permits under review at PA DEP (3 pending).

Key facts

Operator
Edged US / CDE Acquisitions
Location
South Whitehall Township (Lehigh County), Pennsylvania
Application filed
2026-01-28
Stage today
In review

Source
read 2026-10-08

What to do next

Next step: Application filed. Ask the planning office for the hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (6 events)

  • 2025-10-24permit
    Sewage Facilities Planning application submitted to PA DEP under WPC Act 537 Municipal Sewage Planning — DEP status: Pending. · source
  • 2026-01-28permit
    Water Obstruction & Encroachment Pmt application submitted to PA DEP under WRM Water Obstructions & Encroachments (E3902226-002 / eFACTS auth 1556659) — DEP status: Pending. · source
  • 2026-03-11permit
    Notice of Intent to Remediate (Act 2) application submitted to PA DEP under Environmental Cleanup & Brownfields — DEP status: Received. · source
  • 2026-03-30permit
    Notice of Intent to Remediate (Act 2) application submitted to PA DEP under Environmental Cleanup & Brownfields — DEP status: Pending. · source
  • 2026-06-12permit
    Minor Facility Plan Approval New Source Performance Std application submitted to PA DEP under Air Quality (39-00117A / eFACTS auth 1574924) — DEP status: Pending. · source
  • 2026-08-04permit
    Chapter 102 Individual NPDES Permit application submitted to PA DEP under WPC Erosion & Sediment Control (PAD390390 / eFACTS auth 1578878) — DEP status: Pending. · source

Find the paper trail

Find the paper trail (6 filed · 11 places to look)

Permits already on file (6)

Filings we have a source for — the record, not a place to look for one.

  • 2026-08-04
    Chapter 102 Individual NPDES Permit application submitted to PA DEP under WPC Erosion & Sediment Control (PAD390390 / eFACTS auth 1578878) — DEP status: Pending. · source
  • 2026-06-12
    Minor Facility Plan Approval New Source Performance Std application submitted to PA DEP under Air Quality (39-00117A / eFACTS auth 1574924) — DEP status: Pending. · source
  • 2026-03-30
    Notice of Intent to Remediate (Act 2) application submitted to PA DEP under Environmental Cleanup & Brownfields — DEP status: Pending. · source
  • 2026-03-11
    Notice of Intent to Remediate (Act 2) application submitted to PA DEP under Environmental Cleanup & Brownfields — DEP status: Received. · source
  • 2026-01-28
    Water Obstruction & Encroachment Pmt application submitted to PA DEP under WRM Water Obstructions & Encroachments (E3902226-002 / eFACTS auth 1556659) — DEP status: Pending. · source
  • 2025-10-24
    Sewage Facilities Planning application submitted to PA DEP under WPC Act 537 Municipal Sewage Planning — DEP status: Pending. · source

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 40.643, -75.537 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Pennsylvania

Cite this page: GridWatch AI, “Project Atlas”, aigridwatch.com/projects/project-atlas-south-whitehall-township-pa, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).

Toolkit States Tracker Search