Project Taurus (Raeden) In review
Retrofit of an existing building on Garden of the Gods Road into the city's first AI data center, by California-based Raeden. Administratively approved by city staff in June 2026; the planning commission denied residents' appeals after a marathon hearing; two new appeals now send it to City Council, whose hearing must fall between Aug 29 and Sept 28 (likely mid-September - date not yet set). Chelsea Glen neighbors cite power, water, and noise from a prior Bitcoin operation at the site.
Key facts
- Operator
- Raeden
- Location
- Colorado Springs (El Paso County), Colorado
- Application filed
- 2026-06-01
- Stage today
- In review
Source
read 2026-08-07
What to do next
Next step: Application filed. Ask the planning office for the hearing date and request formal notice.
What has happened so far (9 events)
- 2026-04-01announcement
KKTV reported that Oakland, California-based Raeden proposed 'Project Taurus,' a roughly 50-megawatt data center to replace a former Intel manufacturing plant near Garden of the Gods, and that a neighborhood meeting to hear resident concerns was scheduled for April 7, 2026, at the Hyatt Place hotel. · source - 2026-06-01filing
City planning department administratively approved the Project Taurus application in June 2026; neighbors immediately announced an appeal. · source - 2026-06-11filing
KRDO reported the city Planning Department administratively approved the Development Plan Modification on June 11, 2026, for the 21.96-acre former Intel site at 1565 High Tech Way, with residents given until 5 p.m. on June 22 to file appeals. · source - 2026-06-15coverage
KRDO reported Raeden COO Jason Green said the company made voluntary modifications including generator relocation, enhanced noise monitoring, a $1 million bond, and third-party post-construction audits, while Integrity Matters' Dana Duggan criticized that residents were not notified until a day after the June 11 approval. · source - 2026-06-22protest
Per Integrity Matters, a citizen petition requesting a moratorium on data center approvals had gathered 5,349 signatures as of June 22, 2026, and a coalition of 33 appellants led by Katherine Kent and Ron Graham-Becker filed a formal appeal (City File No. DEPN-26-0039) challenging the Project Taurus approval. · source - 2026-06-23filing
Five appeals - including one from Chelsea Glen residents and the transparency group Integrity Matters - met the city's requirements to proceed. · source - 2026-07-23vote
Planning Commission denied the citizens' appeals after a ~14-hour hearing, upholding the approval 6-2. · source - 2026-08-03filing
Two new appeals filed, sending the decision to City Council - the final local authority. Hearing must occur between Aug 29 and Sept 28, 2026. · source - 2026-08-11hearing
KRDO reported the Colorado Springs City Council announced its special meeting to hear the Project Taurus appeal would be held September 17, 2026, at 9 a.m. at the Pikes Peak Center for the Performing Arts, with up to 120 speakers allowed two minutes each. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Colorado CDPHE — Air Pollution Control DivisionThe program page: which permits this state requires, and the office that issues them.
- Search Colorado CDPHE — Air Pollution Control Division for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Colorado Springs (El Paso County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Colorado Springs (El Paso County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Colorado Public Utilities Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 38.900, -104.850 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Recent news
- Colorado Springs may approve its first AI data center – here’s what you need to know about Project Taurus
- Colorado Springs Community-First Data Center Standards
- Residents appeal approval of data center in Colorado Springs
Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 3 headlines archived.
Around here
- Colorado briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Colorado
- CoreSite DE3 (Denver) — Globeville-Elyria-Swansea (Denver) Under construction
Cite this page: GridWatch AI, “Project Taurus (Raeden)”, aigridwatch.com/projects/project-taurus-colorado-springs-co, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).