QTS Dane County In review
Multi-billion dollar, 750MW renewable-powered data center campus in Dane County, Wisconsin.
Key facts
- Operator
- QTS Data Centers
- Size
- 750 MW
- Location
- Dane County, Wisconsin
- Stage today
- In review
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (16 events)
- 2025-07-09announcement
QTS Data Centers began exploring a multi-building data center campus on a 615-acre property in the Town of Vienna, Dane County, holding a public drop-in meeting to introduce the concept. · source - 2025-07-31public-comment
Local residents and officials raised early questions about the scale, water use, and energy demand of the proposed QTS data center campus in rural Dane County. · source - 2025-10-20environmental
Dane County energy office director told Madison sustainability committee the proposed Vienna data center could use about 2.5 times the electricity that all of Dane County currently consumes. · source - 2025-11-01filing
QTS planned to submit a formal zoning/annexation application to the DeForest Village Board, triggering village staff due diligence with outside legal and development experts. · source - 2025-11-14announcement
QTS and UW-Madison announced a $1.5 million Advancing Data Center Sustainability research partnership with the Nelson Institute for Environmental Studies, funding 14 faculty research projects. · source - 2025-11-18announcement
QTS announced a $12 billion, up-to-1,600-acre data center campus in Dane County (Town of Vienna/DeForest), partnering with the Building Trades Council for up to 5,000 union construction jobs and pledging a $50 million community commitment. · source - 2026-01-07protest
More than four hours of public comment at a packed DeForest Village Hall meeting drew opposition to the QTS annexation; a citizen petition sought to require large annexations to go to referendum. · source - 2026-01-13moratorium
Madison Common Council approved a temporary one-year moratorium on zoning approvals for new data centers larger than 10,000 square feet. · source - 2026-01-27report
DeForest village staff recommended the Village Board reject QTS annexation petition, concluding the data center proposal was not feasible in DeForest after QTS declined pre-annexation requirements including a 70%-renewable energy commitment. · source - 2026-01-28withdrawal
QTS withdrew its data center project from consideration in the Village of DeForest following staff recommendation against annexation and sustained community opposition. · source - 2026-01-28utility
Alliant Energy adjusted plans tied to the QTS Greater Madison project as the DeForest annexation collapsed, having previously committed to developing 750 MW of renewable generation. · source - 2026-02-03vote
The DeForest Village Board voted unanimously 7-0 to reject QTS petition to annex nearly 1,600 acres of Town of Vienna farmland, formally ending the DeForest route for the project. · source - 2026-02-12coverage
Democratic state lawmakers proposed a statewide data center moratorium bill and held a day of action, citing the DeForest/QTS fight as a driver of the broader Wisconsin data center policy debate. · source - 2026-04-06moratorium
The Town of Westport (Dane County) enacted a one-year moratorium restricting new data centers to no more than 10,000 square feet, part of a wave of local moratoriums following the QTS controversy. · source - 2026-05-15filing
A resolution was introduced on the Dane County Board establishing an 18-month moratorium on receiving or issuing zoning permits for hyperscale data centers in unincorporated areas. · source - 2026-06-04moratorium
The Dane County Board of Supervisors unanimously approved an 18-month moratorium on zoning permits for hyperscale data centers in unincorporated county areas, running until December 2027. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Wisconsin DNR — Air ManagementThe program page: which permits this state requires, and the office that issues them.
- Search Wisconsin DNR — Air Management for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Dane County planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Dane County property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- MISO (Midwest & Gulf) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Public Service Commission of Wisconsin — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Recent news
Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 1 headline archived.
Around here
- Dane County community briefing — Enactedexpires 2027-12-04
- Wisconsin briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Wisconsin
- Meta Beaver Dam — Beaver Dam Under construction
- Microsoft Fairwater Wisconsin — Mount Pleasant
- OpenAI Stargate Wisconsin — Port Washington Under construction
- Project Nova (Microsoft Caledonia) — Caledonia (Racine County) Withdrawn
Cite this page: GridWatch AI, “QTS Dane County”, aigridwatch.com/projects/qts-dane-county-wi, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).