Project dossier · North Slope Borough, Alaska

STAK Energy North Slope Campus In review

$500M, up to 3GW natural-gas-powered AI data center campus on 715 leased acres ~26 mi south of Deadhorse; received preliminary state land-lease approval, construction targeted summer 2026.

Key facts

Operator
STAK Energy
Size
3,000 MW
Acres
715
Location
North Slope Borough, Alaska
Stage today
In review

Source

What to do next

Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (12 events)

  • 2025-11-01filing
    Stak Energy submitted its initial application to Alaska DNR Division of Oil and Gas for a 50-year state land lease (ADL 422741) covering 715.4 acres off the Dalton Highway near Milepost 390 for a natural-gas-powered AI data center campus; DNR solicited competing bids and none came in. · source
  • 2026-03-12filing
    Stak Energy filed a revised application amending its original lease submission to the Division of Oil and Gas. · source
  • 2026-05-12ruling
    Alaska DNR issued a preliminary best-interest finding for the proposed 50-year land lease to Stak Energy, granting preliminary approval for the 715-acre parcel. · source
  • 2026-05-14coverage
    Alaska Beacon broke the story of the proposed $500 million, up-to-3GW natural-gas-powered Stak Energy data center campus on the North Slope. · source
  • 2026-05-18coverage
    Anchorage Daily News expanded coverage detailing the 715-acre footprint, dry-air cooling advantage, and lack of a firm natural-gas supply deal at time of filing. · source
  • 2026-05-26coverage
    Alaska Public Media reported on the proposal, noting Stak Energy Alaska roots and staffing plans. · source
  • 2026-05-28report
    Northern Alaska Environmental Center published an analysis of the lease documents identifying unresolved risks: incomplete wetland delineation, no permafrost thermal modeling, no bird/caribou surveys, undisclosed lease financial terms, and estimated gas consumption of 128-183 billion cubic feet per year. · source
  • 2026-06-01environmental
    The Alaska Center publicized environmental concerns including potential heat-island warming effects extending up to 6.2 miles, the need for 7 million cubic yards of gravel to raise the site 5-7 feet, and fuel consumption potentially exceeding twice urban Alaska electrical generation; urged residents to file public comments. · source
  • 2026-06-15public-comment
    Original public comment deadline on the DNR preliminary best-interest decision for the Stak Energy lease. · source
  • 2026-07-03protest
    Coverage reported Alaskans had flooded the state comment docket with opposition, including submissions reading "HELL NO! To ANY DATA CENTERS" and "NO AI," ahead of the extended comment deadline. · source
  • 2026-07-07report
    Anchorage Daily News reported more than 500 public comments submitted to DNR, with fewer than a dozen supporting the project and the vast majority opposed; Stak Energy characterized most as form letters. · source
  • 2026-07-17public-comment
    Extended deadline (4:30 p.m.) for public comments on the proposed 50-year land lease; DNR said it would assess comments before issuing a final lease decision. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

  • No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
  • Regulatory Commission of Alaska — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
  • FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
  • Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Cite this page: GridWatch AI, “STAK Energy North Slope Campus”, aigridwatch.com/projects/stak-energy-north-slope-ak, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).