Project dossier · Hale County, Texas

Aligned Data Centers Hale County Under construction

$5B, 540MW campus with 6 facilities in Hale County, Texas. Under construction.

Key facts

Operator
Aligned Data Centers
Size
540 MW
Location
Hale County, Texas
Stage today
Under construction

Source

What to do next

Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.

Build an action pack for this project →

What has happened so far (10 events)

  • 2026-02-27public-comment
    Aligned Data Centers held a community meeting at Interstate 27 and FM 54 north of Abernathy where executives addressed resident concerns about infrastructure, jobs, electricity and water use; Abernathy Mayor Harold Bufe said the city would not risk its drinking water and floated possible city annexation of the site. · source
  • 2026-04-09announcement
    Aligned Data Centers publicly announced Project Caprock, a 540 MW, 313-acre, six-facility data center campus in Hale County just outside Abernathy, projected to bring $5 billion into the regional economy. · source
  • 2026-04-09construction
    Aligned Data Centers broke ground on Project Caprock in Hale County, with Ryan Companies as general contractor and the first building targeted for Q1 2027. · source
  • 2026-04-09utility
    Aligned announced a partnership with Xcel Energy for Project Caprock electrical infrastructure, with Aligned building and funding the dedicated power infrastructure itself to shield local ratepayers from added costs. · source
  • 2026-04-09environmental
    Aligned said Project Caprock will use its closed-loop DeltaFlow liquid cooling system paired with air-cooled heat rejection that recirculates water, produces no wastewater, and is designed to protect the Ogallala Aquifer. · source
  • 2026-07-18coverage
    National coverage of AI data center backlash in rural Texas featured the future data center site near Abernathy as part of reporting on divisions among rural Republicans over water and power impacts. · source
  • 2026-08-03moratorium
    Texas Gov. Greg Abbott directed the PUCT and ERCOT to pause new data center grid interconnections statewide pending an audit — a statewide freeze affecting new-project connections including the Texas Panhandle/South Plains region where Project Caprock sits. · source
  • 2026-08-05report
    Reporting noted regulators and lawmakers still lack clear data on how much water and power data centers statewide consume. · source
  • 2026-08-10coverage
    President Trump publicly criticized Gov. Abbott data center moratorium as a mistake; Abbott responded by touting cooperation with tech companies including Meta and OpenAI. · source
  • 2026-08-14report
    Follow-up reporting found Texas data center audit still lacked specifics on scope and methodology; ERCOT indicated the audit would begin shortly after August 20 and last several months. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Texas

Cite this page: GridWatch AI, “Aligned Data Centers Hale County”, aigridwatch.com/projects/aligned-hale-county-tx, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).

Toolkit States Tracker Search