Project dossier · Shippingport (Beaver County), Pennsylvania

Aligned Shippingport (Project Phoenix) In review

Nearly 2M sq ft, ~$10B natural-gas-powered data center campus on the former Bruce Mansfield coal plant site; land deal ($223.15M) closed July 29, 2026.

Key facts

Operator
Aligned Data Centers
Owner
Frontier Group of Companies
Size
651 ac
Location
Shippingport (Beaver County), Pennsylvania
Stage today
In review

Source

What to do next

Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (17 events)

  • 2022-01-01coverage
    Frontier Group acquired the former Bruce Mansfield coal-fired power plant site (660 acres) from Energy Harbor Corp, cleared coal piles, and began marketing the property as Shippingport Industrial Park. · source
  • 2025-01-01filing
    Shippingport Borough solicitor began drafting the borough initial data-center zoning ordinance in anticipation of large-scale proposals at the former Bruce Mansfield site. · source
  • 2025-03-01vote
    Shippingport Borough Council passed a new data-center zoning ordinance establishing use and permitting rules ahead of Aligned formal application. · source
  • 2025-08-01coverage
    A Vistra subsidiary purchased a 74-acre farm in nearby Hookstown for $4.2 million, underscoring the broader wave of AI/data-center-driven land acquisition around Shippingport and Beaver Valley. · source
  • 2025-09-01public-comment
    Residents and officials raised transparency concerns about Frontier Group plans at a Shippingport borough meeting, prompting Gov. Shapiro to later say too many such projects have been shrouded in secrecy. · source
  • 2025-10-01financing
    BlackRock led a roughly $40 billion deal to acquire Aligned Data Centers, the developer behind the proposed Shippingport Project Phoenix campus. · source
  • 2025-12-05filing
    Aligned Data Centers filed a conditional-use application with Shippingport Borough for Project Phoenix on the former Bruce Mansfield power plant site. · source
  • 2025-12-15hearing
    Aligned held its first public information meeting in Shippingport to present Project Phoenix to residents; a company representative apologized for confusion surrounding the proposal. · source
  • 2026-01-28vote
    Shippingport Borough Council approved most of Aligned conditional-use permit for up to three data center buildings totaling roughly 2 million square feet plus an on-site natural gas power plant; only about four residents attended. · source
  • 2026-02-05announcement
    Coverage detailed Aligned roughly $10 billion Shippingport Industrial Park campus plan on the ~660-acre former Bruce Mansfield site, with conditional use permits approved and the project in pre-construction planning. · source
  • 2026-02-08coverage
    Pittsburgh Post-Gazette reported Beaver Valley becoming a regional data-center target, noting Aligned natural gas plan alongside a separate Vistra-Meta power purchase agreement tied to the Beaver Valley nuclear plant. · source
  • 2026-02-09report
    Detailed site-plan figures: 593 acres, three two-story buildings up to 59 feet tall (1.95 million sq ft combined), a 70-acre natural gas power-generation pad, and 250 parking spaces; six parcels still needed acquisition. · source
  • 2026-02-09permit
    Aligned/Frontier applied for mass grading, NPDES, and stormwater permits plus variances for 59-ft building height, up to 75% woodland clearing, 65-dB operational noise limits, and round-the-clock construction noise. · source
  • 2026-02-09utility
    Frontier Group plan to convert adjacent former Bruce Mansfield coal units to natural gas generation (up to 3.6 GW, ~$3.2 billion via EQT and National Fuel Gas) cited as the eventual power source for the Aligned campus. · source
  • 2026-02-09public-comment
    Mixed local reaction: some welcomed jobs while Beaver County economic development president cautioned that blindly chasing data centers is not the way to go; residents cited property-value and mine-subsidence concerns. · source
  • 2026-06-25vote
    Pennsylvania House voted 197-5 to pass HB 2198 repealing the state Computer Data Center Equipment sales-tax incentive program, projected to cost $188.4 million in FY2026-27 growing to $517 million by 2030. · source
  • 2026-07-29financing
    Aligned Data Centers closed its purchase of 650.89 acres in Shippingport from Frontier Group for $223,150,865 to build its nearly 2-million-square-foot data center campus. · source

Find the paper trail

Find the paper trail (1 filed · 11 places to look)

Permits already on file (1)

Filings we have a source for — the record, not a place to look for one.

  • 2026-02-09
    Aligned/Frontier applied for mass grading, NPDES, and stormwater permits plus variances for 59-ft building height, up to 75% woodland clearing, 65-dB operational noise limits, and round-the-clock construction noise. · source

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Pennsylvania

Cite this page: GridWatch AI, “Aligned Shippingport (Project Phoenix)”, aigridwatch.com/projects/aligned-shippingport-pa, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).