Project dossier · Harwood, North Dakota

Applied Digital Harwood ND Under construction

$3B, 280MW data center in Harwood, North Dakota. Under construction.

Key facts

Operator
Applied Digital
Owner
Applied Digital
Size
280 MW
Location
Harwood, North Dakota
Stage today
Under construction

Source

What to do next

Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.

Build an action pack for this project →

What has happened so far (19 events)

  • 2025-08-18announcement
    Applied Digital announced Polaris Forge 2, a $3 billion, 280MW AI data center campus on 900+ contracted acres southeast of Harwood, ND, with plans to break ground in September 2025. · source
  • 2025-08-25public-comment
    About 300 residents attended a town hall at the Harwood Community Center; some shouted when is the vote? and accused the town of having sold out. · source
  • 2025-08-25protest
    Community members voiced anger and pressed for more disclosure, citing concerns about transparency in the approval process. · source
  • 2025-08-28filing
    City of Fargo moved to annex roughly 800 acres near Harwood including the proposed data center site; Applied Digital said it would formally protest the annexation. · source
  • 2025-09-02rezoning
    Harwood City Council voted unanimously on first reading to rezone roughly 320 acres from agricultural to light industrial, after a contentious session with public shouting. · source
  • 2025-09-10vote
    Harwood City Council gave final approval to rezone the 320-acre site in about 25 minutes at a special meeting, even as Fargo continued to pursue annexation. · source
  • 2025-09-15construction
    Construction crews observed breaking ground on the Polaris Forge 2 site near Harwood. · source
  • 2025-10-22financing
    Applied Digital announced a roughly $5 billion, 15-year, 200MW AI factory lease with an unnamed US-based investment-grade hyperscaler (later reported as Oracle) at Polaris Forge 2, with right of first refusal on an additional 800MW. · source
  • 2025-10-29coverage
    Reporting revealed Harwood and Fargo mayors had signed NDAs with Applied Digital covering project details, raising open-records concerns and prompting draft state legislation to ban such NDAs by public officials. · source
  • 2025-11-24vote
    Harwood City Council voted unanimously to reject a draft agreement proposed by Fargo that would have set conditions in exchange for dropping its annexation attempt. · source
  • 2025-12-08vote
    Fargo City Commission voted unanimously to cancel its annexation of roughly 300 acres including the data center site and voted 4-1 to send a separate disputed annexation into mediation with Harwood. · source
  • 2026-02-01public-comment
    Dakota Resource Council held a public meeting on the Harwood data center drawing about 100 attendees; the group said it wants projects to be transparent and beneficial to host communities. · source
  • 2026-03-10financing
    Applied Digital closed a $2.15 billion private offering of 6.750% senior secured notes (maturing 2031) to fund construction of roughly 200MW at the Harwood campus. · source
  • 2026-03-23utility
    Reporting detailed Applied Digital backing of the Agassiz Transmission Line and Substation project with Minnkota Power Cooperative to deliver the 280MW needed for the Harwood campus. · source
  • 2026-04-02utility
    Minnkota disclosed the cost of the Agassiz transmission line rose from about $75 million to $110 million due to tight timelines and tariffs; Applied Digital will cover the full cost with no charge to other customers. · source
  • 2026-04-29ruling
    North Dakota Public Service Commission approved the $110 million Agassiz Transmission Line and Substation, targeting operational by fall 2026. · source
  • 2026-05-11coverage
    Statewide reporting examined the lack of ND state-level siting authority for data centers, noting the PSC has virtually no say over location, and a failed 2025 bill (HB 1427) that would have granted it. · source
  • 2026-07-13announcement
    Applied Digital confirmed it was expanding its ND footprint and eyeing Oliver County for a third data center campus. · source
  • 2026-08-01coverage
    Harwood residents still felt left in the dark about the data center months after approval, citing the town NDA-driven negotiation process as an example of insufficient transparency. · source

Find the paper trail

Find the paper trail (0 filed · 12 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

  • Search Harwood planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
  • Search Harwood property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in North Dakota

Cite this page: GridWatch AI, “Applied Digital Harwood ND”, aigridwatch.com/projects/applied-digital-harwood-nd, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).