Project dossier · Cave City (Barren County), Kentucky

Cave City data center (Kentucky Industrial Alliance) Awaiting decision

Kentucky Industrial Alliance LLC proposes a data center on a 381-acre project site within its 600+ acres at 2001 Doyle Avenue, about 10 miles from Mammoth Cave National Park; it submitted an application May 11, 2026, and sued the city on June 8 after Cave City adopted a one-year moratorium. The city moved to dismiss on June 29, arguing no actual development plan was ever filed; a July 20 preliminary-injunction hearing was scheduled. Residents fear runoff through the karst into the Mammoth Cave system.

Key facts

Owner
Kentucky Industrial Alliance LLC
Filing LLC
Kentucky Industrial Alliance LLC
Size
381 ac
Location
Cave City (Barren County), Kentucky
Application filed
2026-05-11
Hearing
2026-07-20
Stage today
Awaiting decision

Source
read 2026-08-14

What to do next

Next step: Heard 2026-07-20; decision pending. Call the board clerk for the vote date and get on the notification list.

Build an action pack for this project →

What has happened so far (14 events)

  • 2024-09-11rezoning
    Cave City Council approved the ordinance annexing approximately 245 acres of the former Branstetter property into the city limits, the land later tied to the proposed data center. · source
  • 2026-04-30hearing
    The Joint City-County Planning Commission unanimously approved proposed data center regulations during a public hearing and forwarded them to the Cave City Council. · source
  • 2026-05-11filing
    Kentucky Industrial Alliance LLC submitted a development application for a data center on its 600+ acre property at 2001 Doyle Avenue in Cave City. · source
  • 2026-05-18hearing
    Cave City held the first of two special meetings regarding data centers. · source
  • 2026-05-20vote
    Cave City held a second special meeting and subsequently enacted a 12-month moratorium on data centers. · source
  • 2026-06-08filing
    Kentucky Industrial Alliance LLC sued Cave City, the City Council, and the Joint City-County Planning Commission in Barren County Circuit Court, arguing the one-year data center moratorium violates due process. · source
  • 2026-06-09vote
    The Cave City Council voted to hire outside legal counsel to defend against Kentucky Industrial Alliance's lawsuit. · source
  • 2026-06-29filing
    Cave City's attorneys filed a motion to dismiss, arguing the company never submitted an actual development plan under city ordinances. · source
  • 2026-06-30lawsuit
    Kentucky Industrial Alliance filed a second lawsuit in Barren Circuit Court seeking to void Cave City's September 2024 annexation of about 245 acres, alleging the Shaw Cemetery parcel's owner did not consent as required by KRS 81A.412(1). · source
  • 2026-07-01filing
    The Joint City-County Planning Commission filed its response in the moratorium suit, stating no development plan accompanied the application and that it would take no further action until the litigation concludes. · source
  • 2026-07-18protest
    Cave City residents held a protest against the proposed hyperscale data center near Mammoth Cave National Park. · source
  • 2026-07-18filing
    Attorney Thomas Davis filed the Joint City-County Planning Commission's response to the annexation lawsuit, requesting dismissal with prejudice so the commission could decide applications under its rules and applicable state law. · source
  • 2026-07-20hearing
    A Barren County Circuit Court hearing was scheduled on Kentucky Industrial Alliance's request for a preliminary injunction to temporarily block enforcement of the moratorium. · source
  • 2026-07-21hearing
    A community town hall on the proposed data center was scheduled for July 21 at Austin Tracy Elementary School. · source

Find the paper trail

Find the paper trail (0 filed · 12 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 37.140, -85.960 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Recent news

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 1 headline archived.

Around here

Other tracked projects in Kentucky

Cite this page: GridWatch AI, “Cave City data center (Kentucky Industrial Alliance)”, aigridwatch.com/projects/cave-city-doyle-avenue-data-center, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).