Project dossier · Marble (Cherokee County), North Carolina

CoreWeave Marble NC In review

Chip types: B200. Epoch AI estimates ~65 MW.

Key facts

Operator
CoreWeave
Owner
CoreWeave
Tenant
OpenAI
Size
65 MW
Location
Marble (Cherokee County), North Carolina
Stage today
In review

Source
read 2026-08-14

What to do next

Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (5 events)

  • 2025-07-07announcement
    Core Scientific announced a definitive agreement for CoreWeave to acquire it in an all-stock deal implying roughly $9.0 billion equity value (0.1235 CoreWeave shares per Core Scientific share), giving CoreWeave about 1.3 GW of gross power across Core Scientific's national data center footprint. · source
  • 2025-10-30withdrawal
    Core Scientific announced termination of its merger agreement with CoreWeave after stockholders did not provide the votes necessary to approve the deal, saying it would remain a publicly traded company on Nasdaq under ticker CORZ. · source
  • 2026-01-01vote
    At a Cherokee County commissioners meeting in January 2026, commissioner Ben Adams urged colleagues to renew an expired cryptocurrency moratorium and add AI data centers to the restricted businesses; the proposal did not pass. · source
  • 2026-04-10coverage
    WUNC reported on Cherokee County resident opposition to the conversion of the Marble crypto mine into an AI data center, noting the site plan submitted to the county specified more than 170 diesel generators and that the facility draws water from the municipal supply plus three onsite wells. · source
  • 2026-05-14coverage
    Grist reported on the conversion of the former American Thread plant in Marble from crypto mining to an AI data center consuming as much power as a medium-sized town, noting the site plan included more than 170 diesel generators and that the Core Scientific–CoreWeave merger had fallen through the prior October. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 35.150, -83.950 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in North Carolina

Cite this page: GridWatch AI, “CoreWeave Marble NC”, aigridwatch.com/projects/coreweave-marble-nc, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).

Toolkit States Tracker Search