DataBank Project Indo In review
200MW, $2.4B, 1.1M sq ft data center campus at 218 Industrial Park Road near Atlanta; filed a Development of Regional Impact application and a 288MW grid interconnection request.
Key facts
- Operator
- DataBank
- Size
- 200 MW
- Acres
- 69
- Location
- Cartersville (Bartow County), Georgia
- Stage today
- In review
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (4 events)
- 2026-06-22filing
DataBank Holdings filed a Development of Regional Impact (DRI) application with the Georgia Department of Community Affairs for 'Project Indo,' a proposed 200 MW data center campus on 69 acres at 218 Industrial Park Road, Cartersville, seeking a 288 MW utility grid connection; full build-out is estimated at $2.4 billion with first phase targeted for 2032. · source - 2026-06-25rezoning
DataBank filed a rezoning request with the City of Cartersville to change the 218 Industrial Park Road site from HI (heavy industrial) to T (technology district) to permit the ~1 million-sq-ft data center and on-site power substation; city planner David Hardegree said the request would go before the Planning Commission on August 11, with projected annual tax revenue of $23 million and 60 full-time jobs. · source - 2026-07-07coverage
Northwest Georgia News reported further details on Project Indo, including a DRI-estimated water use of roughly 5,082 gallons per day; Bartow County Administrator Peter Olson and Commissioner Steve Taylor downplayed traffic and water impacts and framed the project as a tax-revenue benefit for the county. · source - 2026-08-11hearing
Cartersville Planning Commission scheduled hearing on DataBank's rezoning request (HI to Technology district) for the Project Indo data center campus at 218 Industrial Park Road. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Georgia EPD — Air Protection BranchThe program page: which permits this state requires, and the office that issues them.
- Search Georgia EPD — Air Protection Branch for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Cartersville (Bartow County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Cartersville (Bartow County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Georgia Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Georgia briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Georgia
- 1155 Powers Ferry Place data center (Prime Storage site) — Marietta (Cobb County) Approved
- Baconton power generation facility (data-center-linked, NextEra-linked) — Baconton (Mitchell County) Approved
- Burkhalter Road data center (4AM Development) — Statesboro (Bulloch County) Awaiting decision
- CoreWeave Dalton 1 & 2 — Dalton
- I-20/Liberty Road Data Center — Douglas County Denied
Cite this page: GridWatch AI, “DataBank Project Indo”, aigridwatch.com/projects/databank-cartersville-ga, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).