Dulles Cloud South Denied
~2,000-acre / 43M sq ft rezoning rejected days after Digital Gateway collapsed.
Key facts
- Size
- 2,000 ac
- Location
- Prince William County, Virginia
- Decided
- 2026-07-08
- Stage today
- Denied
Source
read 2026-08-19
What to do next
Next step: Denied — watch for a re-filing or a scaled-down resubmission; ask the clerk to add you to the notification list.
What has happened so far (1 event)
- 2026-07-08vote
Board rejected rezoning days after Digital Gateway legal fight ended. · source
Find the paper trail
Find the paper trail (0 filed · 12 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Virginia DEQThe program page: which permits this state requires, and the office that issues them.
- Search Virginia DEQ for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Board of County Supervisors agendas & packetsThe meeting packet carries the staff report, site plan and conditions — verified page for this locality.
- Search Prince William County planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Prince William County property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Virginia State Corporation Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 38.780, -77.600 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Recent news
14 stories tracked since 2026-04-08 across 9 outlets. 11× A community is pushing back on a nearby data center. 2× Water use for cooling is straining the local supply. Most recent: “Northern Virginia's Prince William County puts controls on new data center projects” (Data Center Dynamics, 2026-09-25).
- Northern Virginia's Prince William County puts controls on new data center projects
- Prince William County moves to end by-right data centers
- Prince William County supervisors vote to slow data center development
- Prince William County overhauls its approval framework for new data centers
- Prince William County supervisors to take landmark vote on data centers Tuesday
- Prince William County Board To Vote On Restricting Data Center Development
- Tech Giant Files Application For New Data Center In Prince William County: Report
- Microsoft files to build data center campus in Prince William County, Virginia
- Plans for data center campus in Virginia’s Prince William County refiled
- Plans For Up To 5 New Data Centers In Western Prince William County Revived: Report
- As drought grips Virginia, Prince William County challenges hidden data center water use
- As drought grips Virginia, Prince William County challenges hidden data center water use
+2 more on the story tracker.
Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 14 headlines archived.
Around here
- Virginia briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Virginia
- Google Bristow — Bristow (Prince William County), 5 mi
- PW Digital Gateway — Prince William County, 5 mi Withdrawn
- STACK Infrastructure NVA02 — Manassas, 8 mi Under construction
- Amazon Warrenton (Blackwell Road) — Warrenton (Fauquier County), 11 mi Approved
- Google Arcola — Sterling (Loudoun County), 16 mi
Cite this page: GridWatch AI, “Dulles Cloud South”, aigridwatch.com/projects/dulles-cloud-south-va, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).