EdgeCore Shannon Hill campus Approved
697 acres purchased in the Shannon Hill Regional Business Park for a 3.9M sq ft, 1.1+ GW campus - a $17B+ investment announced June 2025, phased over several years. No construction start date or tenants disclosed at announcement. Part of a data-center surge in a small county that already hosts an AWS campus.
Key facts
- Operator
- EdgeCore Digital Infrastructure
- Size
- 1,100 MW
- Acres
- 697
- Location
- Louisa County (Shannon Hill), Virginia
- First proposed
- 2025-06-01
- Stage today
- Approved
Source
read 2026-08-07
What to do next
Next step: Approved — pivot from stopping it to a binding CBA: enforceable caps on noise, water and cost, plus a community benefit.
What has happened so far (24 events)
- 2019-02-19vote
Louisa County Board of Supervisors voted 6-1 to authorize a $2,620,000 budget supplement (Resolution RES-2019-40) for the purchase of approximately 700 acres in the Shannon Hill area for a regional business park, having previously voted to exercise purchase options on January 22, 2019. · source - 2019-03-01filing
Louisa County completed its purchase of 684 acres at the Shannon Hill exit off I-64 for $2.6 million to establish the Shannon Hill Regional Business Park, as reported in March 2019. · source - 2022-01-13incentive
Virginia awarded Louisa County $300,000 through the Virginia Business Ready Sites Program for site readiness at the Shannon Hill Regional Business Park. · source - 2023-01-23incentive
Louisa County received an $11.5 million state grant to bring water infrastructure to the 700-acre Shannon Hill Regional Business Park, the third-largest such grant awarded by the state. · source - 2024-04-01permit
The James River Water Authority received a permit from the U.S. Army Corps of Engineers in April 2024, following an April 8 Memorandum of Agreement, clearing construction of a raw water intake, pump station, and four-mile pipeline on the James River that will serve Shannon Hill Regional Business Park among other areas. · source - 2024-09-04financing
EdgeCore Digital Infrastructure completed a $1.9 billion equity raise led by Partners Group, its third financing transaction of 2024 bringing total capital raised that year to over $4 billion, to support hyperscale data center development across its portfolio including Virginia campuses. · source - 2025-06-01news
EdgeCore announced the land purchase (697 ac, Shannon Hill Regional Business Park) and $17B+ phased campus plan in June 2025; construction timing and tenants undisclosed. · source - 2025-06-25announcement
EdgeCore Digital Infrastructure announced the purchase of 697 acres at Shannon Hill Regional Business Park for $42 million and plans for a 1.1+ GW, 3.9 million sq ft data center campus with $17 billion total investment. · source - 2025-06-25announcement
Governor Youngkin praised the EdgeCore deal; a spokesperson confirmed the commonwealth provided no state incentives, though Virginia had previously awarded $300,000 in site-readiness funds in 2022. · source - 2025-06-25coverage
Bisnow reported Louisa County had invested approximately $29.5 million in utilities infrastructure at Shannon Hill using $13.6 million in grants and $17 million in debt, with the county purchasing the land in 2018 for $2.6 million and rezoning it in 2019 for technology uses. · source - 2025-06-25coverage
CBS19 reported EdgeCore plans a closed-loop air-cooled system with minimal water usage and significant landscape buffers; Rappahannock Electric Cooperative and its affiliate Hyperscale Energy Services will provide power. · source - 2025-06-25coverage
Data Center Dynamics reported EdgeCore's Louisa County campus would total 1.1 GW across 3.1 million square feet and six buildings on 697 acres, with power provided by Rappahannock Electric Cooperative. · source - 2025-06-26coverage
Information Charlottesville reported the Shannon Hill sale closed for $42 million; IDA Chairman Dustin Madison stated the announcement marks a realization of the park's full benefits; proceeds will pay down county debt early. · source - 2025-06-30coverage
Local newsletter reported that EdgeCore's Shannon Hill campus will draw water from the James River via a pipeline expected mid-2026, not from the local Northeast Creek Reservoir, differentiating it from the concurrent AWS proposal. · source - 2025-07-14protest
Louisa County residents mobilized against data center expansion with a Facebook group of nearly 500 members, a petition with over 660 signatures, and yard signs reading 'Don't Loudoun my Louisa'; opposition focused on the concurrent AWS proposal but reflected broader concern about all data center development in the county including EdgeCore. · source - 2025-10-27coverage
Engage Louisa reported that EdgeCore Digital Infrastructure plans to develop a third data center campus at Shannon Hill Regional Business Park, in the context of the Board of Supervisors unanimously approving a separate performance agreement with AWS. · source - 2025-12-01vote
Louisa County Board of Supervisors unanimously approved a performance agreement with EdgeCore providing annual performance grants of 15% of real and business personal property tax revenue, capped at $15 million total, with payments from 2027 through 2041. · source - 2025-12-01coverage
The Piedmont Environmental Council listed the December 1 Louisa County Board of Supervisors meeting agenda as including a resolution to approve a local performance agreement with EdgeCore, the data center company developing Shannon Hill Regional Business Park. · source - 2025-12-02coverage
GovTech reported Louisa County sold Shannon Hill to EdgeCore and proceeded with the project despite resident concerns, contrasting it with Amazon's separate withdrawal under stronger community opposition. · source - 2026-01-13announcement
EdgeCore reported entering 2026 with 1.8 GW of capacity delivered or under development across six markets including Louisa County, with $5.9 billion in equity and debt committed and $16.1 billion planned for future development. · source - 2026-04-06financing
Louisa County Board of Supervisors moved to appropriate $33 million from Shannon Hill sale proceeds for water and wastewater infrastructure upgrades -- $11.5 million for a clarifier at Ferncliff Water Treatment Plant and $21.5 million for New Bridge Wastewater Treatment Plant expansion -- paying cash rather than issuing new debt. · source - 2026-06-22coverage
Louisa County Supervisor Manning Woodward stated EdgeCore will operate behind-the-meter power generation at Shannon Hill rather than drawing from the grid; gas-fired generation is the near-term option, with small modular reactors described as far off. · source - 2026-06-29incentive
Virginia's state budget deal preserved the data center sales tax exemption through 2035, while introducing a new energy consumption tax of 1.1 cents per kilowatt-hour capped at $600 million annually; Louisa County Board Chair Duane Adams praised the decision as maintaining the state's commitment to the industry. · source - 2026-08-01permit
U.S. Army Corps of Engineers Norfolk District published public notice NAO-2025-00089 / MRC-2026-1381 for EdgeCore Louisa Phase 2, proposing fill of 4.20 acres of wetlands and 6,302 linear feet of stream for three data center buildings and substations on 187 acres, filed via EDI Louisa 1, LLC. · source
Find the paper trail
Find the paper trail (2 filed · 11 places to look)
Permits already on file (2)
Filings we have a source for — the record, not a place to look for one.
- 2026-08-01
U.S. Army Corps of Engineers Norfolk District published public notice NAO-2025-00089 / MRC-2026-1381 for EdgeCore Louisa Phase 2, proposing fill of 4.20 acres of wetlands and 6,302 linear feet of stream for three data center buildings and substations on 187 acres, filed via EDI Louisa 1, LLC. · source - 2024-04-01
The James River Water Authority received a permit from the U.S. Army Corps of Engineers in April 2024, following an April 8 Memorandum of Agreement, clearing construction of a raw water intake, pump station, and four-mile pipeline on the James River that will serve Shannon Hill Regional Business Park among other areas. · source
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Virginia DEQThe program page: which permits this state requires, and the office that issues them.
- Search Virginia DEQ for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Louisa County (Shannon Hill) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Louisa County (Shannon Hill) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Virginia State Corporation Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 37.870, -78.080 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Virginia briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Virginia
- Mountain Road Technology Park — Hanover County, 34 mi Denied
- Red Ace data center campus (Keyser Road) — Culpeper County, 43 mi Approved
- QTS Richmond 1 — Sandston (Henrico County), 48 mi
- QTS Richmond 2 — Sandston (Henrico County), 48 mi
- QTS Richmond 3 — Sandston (Henrico County), 48 mi Under construction
Cite this page: GridWatch AI, “EdgeCore Shannon Hill campus”, aigridwatch.com/projects/edgecore-louisa-county-va, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.