QTS Richmond 3 Under construction
Epoch AI estimates ~144 MW.
Key facts
- Size
- 144 MW
- Location
- Sandston (Henrico County), Virginia
- Stage today
- Under construction
Source
read 2026-08-14
What to do next
Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.
What has happened so far (6 events)
- 2022-07-13announcement
QTS announced acquisition of 200 acres at its Richmond Mega Data Center campus for an expansion of up to 240 MW across 1.5 million square feet of additional capacity at the White Oak Technology Park in Henrico County. · source - 2022-08-12coverage
Data Center Frontier reported QTS acquired 200 acres at its Richmond campus in Henrico County for expansion of up to 240 MW across 1.5 million square feet. · source - 2022-12-13construction
QTS blog post documented construction progress on two new multi-story data centers at Richmond 2 (DC1 at 36 MW and DC2 at 36 MW), noting QTS Richmond owns 200+ acres of land for future growth capacity. · source - 2024-07-19financing
QTS completed approximately $137 million in land purchases for the White Oak Technology Park II site, including $118.8 million for 397 acres from Hourigan LLC and a prior December 2023 purchase of approximately 225 acres for $18 million; Henrico County Board of Supervisors had approved rezoning of the 622-acre site on May 14, 2024. · source - 2026-04-02permit
The Federal Permitting Improvement Steering Council granted FAST-41 coverage to QTS Richmond Technology Park Data Center 5 (RIC5), the first data center project to receive this federal permitting coordination; anticipated construction start is January 2028. · source - 2026-05-18coverage
Richmond BizSense reported QTS is progressing on a 1,100-acre expansion adding 17 buildings across two new campuses (RIC4 and RIC5), totaling nearly 8 million square feet, with development plans approved by Henrico County; QTS already operates 12 buildings spanning over 3 million square feet at the site. · source
Find the paper trail
Find the paper trail (1 filed · 11 places to look)
Permits already on file (1)
Filings we have a source for — the record, not a place to look for one.
- 2026-04-02
The Federal Permitting Improvement Steering Council granted FAST-41 coverage to QTS Richmond Technology Park Data Center 5 (RIC5), the first data center project to receive this federal permitting coordination; anticipated construction start is January 2028. · source
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Virginia DEQThe program page: which permits this state requires, and the office that issues them.
- Search Virginia DEQ for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Sandston (Henrico County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Sandston (Henrico County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Virginia State Corporation Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 37.520, -77.330 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Virginia briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Virginia
- QTS Richmond 1 — Sandston (Henrico County), 0 mi
- QTS Richmond 2 — Sandston (Henrico County), 0 mi
- CoreWeave Chester VA — Chester (Chesterfield County), 12 mi
- Mountain Road Technology Park — Hanover County, 18 mi Denied
- EdgeCore Shannon Hill campus — Louisa County (Shannon Hill), 48 mi Approved
Cite this page: GridWatch AI, “QTS Richmond 3”, aigridwatch.com/projects/qts-richmond-3, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).