Project dossier · Toney (Madison County), Alabama

Meta Huntsville Under construction

Chip types: B300. Epoch AI estimates ~146 MW.

Key facts

Operator
Meta
Owner
Meta
Size
146 MW
Location
Toney (Madison County), Alabama
Stage today
Under construction

Source
read 2026-08-14

What to do next

Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.

Build an action pack for this project →

What has happened so far (4 events)

  • 2018-05-24vote
    Huntsville City Council unanimously approved the sale of 340 acres in the North Huntsville Industrial Park to Facebook's project entity, Starbelt LLC, for $8.5 million. · source
  • 2018-06-14announcement
    Governor Kay Ivey announced Facebook would invest $750 million to build a data center in Huntsville, projected to create about 100 jobs at an average annual salary of $80,000, with Facebook set to receive an estimated $86.25 million in Alabama Jobs Act credits over 10 years. · source
  • 2022-12-16construction
    Meta announced a temporary work stoppage on the Huntsville data center expansion, with a company spokesperson attributing it to changes in the data center's design. · source
  • 2022-12-20coverage
    Meta confirmed it halted construction on a portion of its $1.5 billion Huntsville expansion to change the facility's design, part of a broader pullback that also paused a Temple, Texas project and canceled a planned Odense, Denmark facility amid the company's shift toward AI infrastructure. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

  • No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
  • Alabama Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
  • FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
  • Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 34.790, -86.750 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Alabama

Cite this page: GridWatch AI, “Meta Huntsville”, aigridwatch.com/projects/meta-huntsville, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).