Project dossier · Rosemount, Minnesota

Meta Rosemount Under construction

Chip types: B200. Epoch AI estimates ~178 MW.

Key facts

Operator
Meta
Owner
Meta
Size
178 MW
Location
Rosemount, Minnesota
Stage today
Under construction

Source
read 2026-08-14

What to do next

Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.

Build an action pack for this project →

What has happened so far (11 events)

  • 2023-09-01coverage
    Plans emerged in September 2023 that Meta intended to purchase University of Minnesota land in Rosemount for a $700 million data center, disclosed through state filings. · source
  • 2023-09-07vote
    The University of Minnesota Board of Regents approved selling approximately 280 acres of UMore Park land to Meta for $39.7 million for the data center project. · source
  • 2023-12-21vote
    Rosemount City Council voted unanimously to approve Meta's data center, rezoning the 280-acre UMore Park parcel from agricultural to business park planned development. · source
  • 2024-01-06coverage
    Alpha News reported that Rosemount approved Meta's 750,000-sq-ft data center despite residents' concerns about soil contaminants from the site's WWII munitions history, 24/7 low-frequency noise, and water usage during local restrictions; the filing entity is Jimnist LLC. · source
  • 2024-03-14announcement
    Meta officially announced its Rosemount data center: a 715,000-sq-ft, $800+ million facility optimized for AI workloads, targeting LEED Gold certification, 100% renewable energy, approximately 100 permanent jobs and over 1,000 peak construction jobs, with Mortenson as general contractor. · source
  • 2024-03-14coverage
    Governor Tim Walz held a press conference announcing Meta's Rosemount data center, calling it Meta's 19th in the U.S. and 23rd worldwide, with a 2026 opening target. · source
  • 2025-02-18filing
    Meta purchased approximately 200 additional acres of land near its Rosemount data center site for $70 million, expanding beyond the original 280-acre UMore Park parcel. · source
  • 2025-10-17filing
    Meta acquired another 14-acre plot off Blaine Avenue East near 145th Street in Rosemount for $5 million via subsidiary Jimnist, bringing total known land holdings to at least 494 acres. · source
  • 2026-03-30construction
    Meta and Amrize deployed an AI-optimized concrete mix (BOxCrete) for the Rosemount data center foundation, achieving full structural strength 43% faster and reducing cracking risk by nearly 10%; the mix was qualified for additional areas of the facility. · source
  • 2026-04-30moratorium
    Rosemount halted new data center proposals with a moratorium, pausing discussion of additional facilities beyond Meta's already-approved project. · source
  • 2026-07-02construction
    InForum reported that Minnesota's first hyperscale data center is nearing completion in Rosemount. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

  • Search Rosemount planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
  • Search Rosemount property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 44.720, -93.070 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Minnesota

Cite this page: GridWatch AI, “Meta Rosemount”, aigridwatch.com/projects/meta-rosemount, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).