Project dossier · Monticello (Wright County), Minnesota

Monticello Tech data center campus In review

Monticello Tech, led by Frattalone Companies CEO Nick Frattalone, filed a land-use application with the City of Monticello, Minnesota on 2026-07-07 seeking rezoning to a Data Center Planned Unit Development district plus preliminary plat and conditional use permit approvals for a site south of 85th Street NE and east of Highway 25. The application describes 547 acres (364 developable), up to 3 million sq ft, as many as 8 principal buildings, about 75,000 gallons/day of water, and a connection to Xcel Energy's 345 kV system; the developer projects about $7 million in annual property tax at full buildout, with construction possibly starting Q1 2028. The eventual operator is not identified. City staff had until 2026-08-21 to determine whether the application is complete; Minnesota law then allows a 60-day review, extendable to 120 days.

Key facts

Filing LLC
Monticello Tech
Size
547 ac
Location
Monticello (Wright County), Minnesota
Application filed
2026-07-07
Stage today
In review

Source
read 2026-08-14

What to do next

Next step: Application filed. Ask the planning office for the hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (14 events)

  • 2025-08-19hearing
    The Monticello Planning Commission opened a public hearing on a proposed data center zoning ordinance (DCPUD) at the Mississippi Room of the Monticello Community Center, drawing large crowds. · source
  • 2025-09-02hearing
    The Monticello Planning Commission held a continued public hearing on the DCPUD zoning ordinance; the hearing closed without a vote and the ordinance was tabled. · source
  • 2025-11-01environmental
    In November 2025, the City of Monticello published the Draft Alternative Urban Areawide Review (AUAR) for a 550-acre industrial area and opened a 30-day public comment period running November 18 through December 18, 2025. · source
  • 2026-01-26vote
    The Monticello City Council unanimously adopted the Final AUAR and Mitigation Plan for the 550-acre Monticello Industrial area, covering two development scenarios including a 3-million-square-foot technology campus. · source
  • 2026-02-03vote
    The Monticello Planning Commission unanimously recommended approval of the DCPUD (Data Center Planned Unit Development) zoning ordinance to the City Council. · source
  • 2026-02-25lawsuit
    The Minnesota Center for Environmental Advocacy (MCEA) filed suit in Wright County District Court (Case No. 86-CV-26-1130) against the City of Monticello and Monticello Tech LLC, challenging the adequacy of the AUAR environmental review. · source
  • 2026-03-08protest
    Close to 500 Monticello residents gathered at a local park to sign a statutory citizen petition seeking additional environmental review of the proposed Monticello Tech data center project. · source
  • 2026-04-27vote
    The Monticello City Council approved the DCPUD zoning ordinance in a 4-1 vote, establishing setback, screening, infrastructure, and environmental standards for data center development; Council Member Charlotte Gabler cast the sole dissenting vote. · source
  • 2026-04-28coverage
    MPR News reported on the newly approved Monticello DCPUD ordinance, noting data centers face new restrictions while the ordinance opens the door to building in Monticello. · source
  • 2026-04-30ruling
    Wright County District Court Judge Suzanne Bollman issued a scheduling order in the MCEA v. Monticello lawsuit, setting discovery to conclude by October 15, 2026 and a pretrial conference for December 29, 2026. · source
  • 2026-06-29coverage
    Monticello Times reported that Monticello Tech was targeting a July application for its proposed data center site, with the city confirming no formal application had yet been submitted and pre-application discussions were ongoing. · source
  • 2026-07-07filing
    Monticello Tech submitted its formal data center application to the City of Monticello, Minnesota, ahead of the Planning Commission's tentative Aug. 4 agenda. · source
  • 2026-07-20filing
    The City of Monticello issued a nine-page letter deeming Monticello Tech's July 6 land-use applications incomplete, citing inconsistencies in applicant information, missing survey certifications, incomplete project narratives, and absent engineering and environmental documentation. · source
  • 2026-08-03filing
    Monticello Tech submitted a revised application with hundreds of pages of engineering plans and technical studies, detailing a 547-acre campus (364 acres developable) with up to 3 million sq ft across eight buildings, air-cooled design using approximately 75,000 gallons of water daily, and an estimated $73.5 million in infrastructure costs funded by the developer. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 45.310, -93.790 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Minnesota

Cite this page: GridWatch AI, “Monticello Tech data center campus”, aigridwatch.com/projects/monticello-tech-monticello-mn, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).

Toolkit States Tracker Search