Project dossier · Temple, Texas

Meta Temple Operating

Chip types: B300. Epoch AI estimates ~152 MW.

Key facts

Operator
Meta
Owner
Meta
Size
152 MW
Location
Temple, Texas
Stage today
Operating

Source
read 2026-08-14

What to do next

Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.

Build an action pack for this project →

What has happened so far (11 events)

  • 2022-03-31announcement
    Meta announces it will build an $800 million, approximately 900,000-square-foot hyperscale data center on 393 acres off NW H K Dodgen Loop and Industrial Blvd in Temple, supporting about 100 permanent jobs with construction starting in spring 2022. · source
  • 2022-03-31announcement
    City of Temple announces Meta's new hyperscale data center; Mayor Tim Davis calls it a significant win for the community; Temple EDC President Adrian Cannady and Governor Greg Abbott also praised the project. · source
  • 2022-12-15construction
    KWTX reports Meta is pausing construction at its Temple facility, stating it decided to change the design; a spokesperson said Meta remains committed to the community and local stakeholders. · source
  • 2022-12-19coverage
    Construction Dive reports Meta paused construction at its $800 million Temple data center to change the design; the pause followed Meta's November 2022 mass layoffs; general contractor is JE Dunn. · source
  • 2023-10-20construction
    Construction Review Online reports Meta restarted work at Temple and Kuna after halting globally to redesign data centers for denser GPU installations for AI applications. · source
  • 2023-10-23construction
    Construction Dive reports JE Dunn resumed construction on Meta's Temple data center after the December 2022 pause; Meta says the AI-optimized redesign is 31% less expensive and takes half the time to build; completion shifted from 2025 to 2026. · source
  • 2025-04-04coverage
    GovTech reports Minnesota-based Oppidan Investment Co. purchased 10 acres from the Temple Economic Development Corp. in March 2025 and plans a $31 million, 61,554-square-foot data center at 2325 Eberhardt Road directly across from Meta's campus. · source
  • 2026-07-22operational
    Meta officially opens its $1.2 billion AI-optimized data center on Industrial Boulevard in Temple; the 760,000-square-foot, two-building campus supports nearly 100 operations jobs and employed over 1,200 trade workers at peak construction. · source
  • 2026-07-22incentive
    At the opening event Meta announced a $400,000 grant as part of $1.7 million in total direct funding to Bell County-area schools and nonprofits, plus $8 million in local public water and wastewater improvements. · source
  • 2026-07-30coverage
    Spectrum News reports the Temple facility is Meta's first AI-optimized data center globally to go online; Meta's Bradley Davis says it uses a closed-loop liquid cooling system requiring zero water for most of the year; Joe Royer of Temple Stands Together community opposition group raised concerns about water consumption, power demand, and heat island effects. · source
  • 2026-08-05coverage
    Texas Scorecard reports Meta declined to specify exact water and power requirements for the Temple facility; community opposition voiced on Meta's Facebook page with commenters stating they do not want the data center. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

  • Search Temple planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
  • Search Temple property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 31.110, -97.370 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Recent news

4 stories tracked since 2026-08-16 across 3 outlets. 3× A community is pushing back on a nearby data center. 1× Water use for cooling is straining the local supply. Most recent: “Rowan’s $4.2 billion Temple data center campus advances as water, power questions persist” (The Killeen Daily Herald, 2026-09-13).

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 4 headlines archived.

Around here

Other tracked projects in Texas

Cite this page: GridWatch AI, “Meta Temple”, aigridwatch.com/projects/meta-temple, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).