Project dossier · Milam County, Texas

OpenAI Stargate Milam Operating

Part of Stargate.

Key facts

Operator
Softbank
Owner
Softbank
Tenant
OpenAI
Location
Milam County, Texas
Stage today
Operating

Source
read 2026-08-14

What to do next

Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.

Build an action pack for this project →

What has happened so far (17 events)

  • 2025-01-21announcement
    President Trump announced the Stargate Project, a $500 billion AI infrastructure joint venture by OpenAI, SoftBank, and Oracle, with initial deployment in Texas. · source
  • 2025-01-28announcement
    Data Center Dynamics reported that solar power and battery storage systems are planned for the Stargate AI data center campus in Milam County. · source
  • 2025-05-12announcement
    Austin Business Journal reported a $3 billion data center campus planned in Milam County by SB Energy, before a tenant had been publicly identified. · source
  • 2025-06-09coverage
    The Real Deal reported that SB Energy's planned $3B Milam County data center was still searching for an end user and seeking tax breaks. · source
  • 2025-09-23announcement
    OpenAI, Oracle, and SoftBank announced an expansion of Stargate with five new AI data center sites across the U.S., including the Milam County, Texas campus. · source
  • 2025-09-25coverage
    Austin Business Journal reported that OpenAI would occupy the planned $3B Milam County data center hub as part of the Stargate project. · source
  • 2025-12-03incentive
    Austin Business Journal reported the OpenAI data center could create hundreds of jobs as part of a $135 million incentive deal in Milam County. · source
  • 2026-01-09financing
    OpenAI and SoftBank Group each invested $500 million in SB Energy; OpenAI leased 1.2 GW of data center capacity for initial buildout in Milam County, Texas, with facilities expected to enter service starting in 2026. · source
  • 2026-01-12coverage
    Data Center Dynamics reported that SoftBank's SB Energy would build and operate OpenAI's 1.2 GW Stargate data center in Milam County, Texas. · source
  • 2026-02-10incentive
    Milam County Commissioners Court approved a tax abatement for a new data center, as reported by KXXV. · source
  • 2026-03-19coverage
    Austin Business Journal reported hints connecting a Silicon Valley company to the takeover of the old 3M campus in Milam County for data center use linked to Stargate. · source
  • 2026-04-17coverage
    MySA reported that data center developers made nearly $500 million in moves in Central Texas towns amid water concerns in the Milam County area. · source
  • 2026-04-22permit
    Data Center Dynamics reported that OpenAI Stargate's Milam County 'Freebird' data center first phase would span 548,950 square feet. · source
  • 2026-05-12rezoning
    The Texas Tribune reported that a Texas county paused data center construction in rural areas for one year, in response to rapid data center expansion in the region. · source
  • 2026-06-16filing
    Austin Business Journal reported that one of the world's largest companies (linked to SoftBank) purchased approximately 4,700 acres in Milam County in a detail-sparse land transaction. · source
  • 2026-08-07construction
    KCENTV reported that rock trucks driving through downtown Temple were traced to the $470 million OpenAI data center construction project in Milam County. · source
  • 2026-08-12operational
    SB Energy committed to comply with Governor Abbott's data center transparency and accountability standards for Texas, alongside Core Scientific and Vantage Data Centers. · source

Find the paper trail

Find the paper trail (1 filed · 11 places to look)

Permits already on file (1)

Filings we have a source for — the record, not a place to look for one.

  • 2026-04-22
    Data Center Dynamics reported that OpenAI Stargate's Milam County 'Freebird' data center first phase would span 548,950 square feet. · source

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 30.750, -96.900 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Recent news

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 1 headline archived.

Around here

Other tracked projects in Texas

Cite this page: GridWatch AI, “OpenAI Stargate Milam”, aigridwatch.com/projects/openai-stargate-milam, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).