Microsoft Three Mile Island (Crane Clean Energy Center) In review
$1.6B power purchase agreement to restart TMI Unit 1 (renamed Crane Clean Energy Center) by 2028; Microsoft will buy 100% of the 835MW nuclear output for 20 years to power its AI data centers.
Key facts
- Operator
- Constellation Energy
- Owner
- Constellation Energy
- Tenant
- Microsoft
- Size
- 835 MW
- Location
- Londonderry Township (Dauphin County), Pennsylvania
- Stage today
- In review
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (19 events)
- 2024-09-04protest
Pennsylvania anti-nuclear activists began organizing to oppose the restart, citing safety and evacuation concerns tied to the 1979 TMI-2 accident. · source - 2024-09-20announcement
Constellation Energy announced a 20-year power purchase agreement with Microsoft to restart the 835 MW Three Mile Island Unit 1, renamed the Crane Clean Energy Center, to supply carbon-free power for Microsoft data centers; the deal is expected to create ~3,400 jobs and add $16 billion to Pennsylvania GDP. · source - 2024-09-25coverage
Local reporting captured mixed community reactions in Londonderry Township/Dauphin County, with labor groups voicing support while some residents raised fear of another accident. · source - 2024-10-25hearing
Constellation laid out its reopening timeline at a public hearing, telling regulators and residents it aimed to have Unit 1 producing power again by 2027-2028. · source - 2024-11-04filing
Constellation submitted its initial restart application to the Nuclear Regulatory Commission for Three Mile Island Unit 1 (Crane Clean Energy Center). · source - 2025-03-20environmental
Constellation began evaluating the environmental impacts of the restart as part of the NRC review process, covering water use from the Susquehanna River, air quality, and spent fuel management. · source - 2025-04-03lawsuit
Activist Gene Stilp sued Dauphin County commissioners and the Public Safety Department, alleging misuse of taxpayer funds to promote the plant restart. · source - 2025-05-06filing
The NRC formally accepted Constellation restart request for Three Mile Island Unit 1 for detailed technical review. · source - 2025-08-01public-comment
Residents told federal regulators the NRC review process feels like a charade, pressing concerns about safety, evacuation planning, and environmental impact at a public forum near the plant. · source - 2025-08-06hearing
The NRC held a second public meeting, this one virtual, allowing community members nationwide to comment on the proposed restart of the Crane Clean Energy Center reactor. · source - 2025-08-15filing
NRC staff issued a Request for Additional Information (RAI) to Constellation as part of the technical review of the Unit 1 restart application. · source - 2025-09-15filing
Constellation submitted its response to the NRC Request for Additional Information regarding the Crane Clean Energy Center restart. · source - 2025-10-06filing
NRC docket correspondence addressed to Constellation Energy regarding the Crane Clean Energy Center restart review. · source - 2025-11-18financing
The U.S. Department of Energy closed a $1 billion loan to Constellation Energy to help finance the roughly $1.6 billion restart of Three Mile Island Unit 1/Crane Clean Energy Center. · source - 2025-12-18coverage
U.S. Energy Secretary Chris Wright touted the $1 billion DOE loan for the Three Mile Island restart as delivering on the Trump administration nuclear energy promises. · source - 2026-04-21filing
PJM independent market monitor Monitoring Analytics filed comments with FERC opposing Constellation requested tariff waivers for the Crane restart. · source - 2026-06-01ruling
FERC approved a waiver allowing Constellation to transfer 760 MW of Capacity Interconnection Rights from its Eddystone plant to the Crane Clean Energy Center, over the objection of PJM independent market monitor. · source - 2026-07-28report
The NRC issued draft environmental assessment findings that the Crane Clean Energy Center restart would have no significant environmental impact, opening a public comment period. · source - 2026-07-28coverage
Reporting noted continued community concern as the Crane nuclear plant restart progressed toward its targeted 2027 date, including concerns about reliance on the Susquehanna River amid climate-driven flood risk. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Pennsylvania DEPThe program page: which permits this state requires, and the office that issues them.
- DEP Data Center Permit Tracker (the only state register built for data centers — it already feeds this tracker)Searchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Londonderry Township (Dauphin County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Londonderry Township (Dauphin County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Pennsylvania Public Utility Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Pennsylvania briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Pennsylvania
- 4-3 Salem Township Data Center — Salem Township (Luzerne County) Rumored
- 900 Conshohocken Road data center (former Cleveland-Cliffs steel mill) — Plymouth Township (Montgomery County) Awaiting decision
- AWS Berwick — Berwick Under construction
- AWS Falls Township campus (Keystone Trade Center) — Falls Township (Bucks County) Approved
- AWS Salem Township campus (Susquehanna nuclear plant) — Salem Township (Luzerne County) Under construction
Cite this page: GridWatch AI, “Microsoft Three Mile Island (Crane Clean Energy Center)”, aigridwatch.com/projects/microsoft-three-mile-island-pa, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).