NE Edge Millstone (Waterford) Withdrawn
1.5M-sq-ft data center proposed to draw power directly from Millstone nuclear plant; host-fee agreement lapsed after nearly 3 years of local opposition, effectively ending the project.
Key facts
- Operator
- NE Edge-Waterford LLC
- Owner
- Dominion Energy Nuclear Connecticut
- Size
- 300 MW
- Location
- Waterford, Connecticut
- Stage today
- Withdrawn
What to do next
Next step: Withdrawn — confirm it is dead in the record and watch for the same site resurfacing under a new name or LLC.
What has happened so far (16 events)
- 2023-02-15announcement
NE Edge, managed by George A. McLaughlin III, publicly proposed a 1.5M-sq-ft, ~300MW data center on Dominion Energy's Millstone Power Station property in Waterford, CT, drawing power directly from the nuclear plant. · source - 2023-02-23announcement
NE Edge detailed plans for a two-building data center at Millstone, committing to pay Waterford $231 million over 30 years in lieu of property taxes. · source - 2023-03-01vote
Waterford's Representative Town Meeting and First Selectman Rob Brule unanimously approved the host fee agreement with NE Edge, which included guidelines on sound and environmental impact. · source - 2023-03-17filing
NE Edge-Waterford, LLC and the Town of Waterford signed a Data Center Host Municipality Fee Agreement committing NE Edge to pay $231M in lieu-of-tax fees over 30 years, with a clause requiring building permits by March 2026. · source - 2023-08-24filing
NE Edge purchased a parcel of land in Connecticut connected to the Millstone-area data center development. · source - 2023-12-21filing
Dominion Energy Nuclear Connecticut filed Petition No. 1586 with the CT Siting Council seeking a declaratory ruling that no new Certificate of Environmental Compatibility was required to revise the Millstone site boundary to lease parcels to NE Edge. · source - 2024-01-01ruling
The Connecticut Siting Council declined to issue Dominion's requested declaratory ruling on the Millstone site boundary revision, finding it premature — a key setback for the NE Edge project. · source - 2024-01-18public-comment
Shoreline residents raised concerns at a town meeting about noise, property values, electric rates, and wildlife impacts; opposition group Concerned Citizens of Waterford and East Lyme (CCWEL), with over 50 members, was active in opposing the site. · source - 2024-01-19coverage
CT Mirror reported on the Millstone-powered data center proposal, detailing the project's direct power arrangement with Dominion and mounting community and regulatory scrutiny. · source - 2024-03-22vote
CT legislature's Energy and Technology Committee voted 12-3 to advance a bill requiring ISO New England and local utilities to study grid impact of the NE Edge behind-the-meter data center. · source - 2024-05-17public-comment
Waterford opponents petitioned the U.S. Nuclear Regulatory Commission to intervene and block the NE Edge proposal, citing concerns tied to proximity to the Millstone nuclear plant. · source - 2024-09-04coverage
Coverage described NE Edge as a hyperscale facility for AI training driven by ~300MW of power (about 15% of Millstone's output), unprecedented in scale for Connecticut. · source - 2025-04-17vote
Waterford's Board of Selectmen voted 2-1 to permit NE Edge, LLC to assign its host fee agreement to a subsidiary company, NE Edge-Waterford, LLC. · source - 2026-02-26coverage
U.S. Sen. Richard Blumenthal teamed up with a Republican senator on federal legislation to rein in data centers, amid continued Connecticut concern over projects like the Waterford proposal. · source - 2026-03-17withdrawal
The deadline for NE Edge to obtain building permits passed without the company meeting it; Waterford First Selectman Rob Brule announced the host fee agreement had ended, effectively killing the project after nearly three years of local opposition. · source - 2026-04-15coverage
CT Mirror published a review of the full arc of the NE Edge fight, characterizing it as a defeated Connecticut data center project after sustained community and regulatory resistance. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Connecticut DEEPThe program page: which permits this state requires, and the office that issues them.
- Search Connecticut DEEP for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Waterford planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Waterford property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- ISO New England — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Connecticut Public Utilities Regulatory Authority — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Connecticut briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Connecticut
- Atlas Capital Bloomfield — Bloomfield In review
Cite this page: GridWatch AI, “NE Edge Millstone (Waterford)”, aigridwatch.com/projects/ne-edge-waterford-ct, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).