Project dossier · Santa Teresa, New Mexico

OpenAI Stargate New Mexico In review

Part of Stargate.

Key facts

Operator
Oracle
Owner
Oracle
Tenant
OpenAI
Location
Santa Teresa, New Mexico
Stage today
In review

Source
read 2026-08-14

What to do next

Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.

Build an action pack for this project →

What has happened so far (8 events)

  • 2025-02-25announcement
    Governor Michelle Lujan Grisham announced a partnership with BorderPlex Digital Assets to build a $5 billion digital infrastructure campus in Santa Teresa, expected to create 1,000 jobs — the first announcement of the site that would become Project Jupiter. · source
  • 2025-09-19vote
    Dona Ana County Board of County Commissioners voted 4-1 to approve an ordinance authorizing issuance of up to $165 billion in Industrial Revenue Bonds for Project Jupiter, including an initial $50 billion investment within five years, a 30-year property-tax abatement offset by PILOT payments, $50 million for water/wastewater infrastructure, and a $6.9 million community investment fund. · source
  • 2025-09-23announcement
    TechCrunch reported OpenAI is building five new Stargate data centers with Oracle and SoftBank, bringing Stargate's planned capacity to 7 gigawatts; Dona Ana County, New Mexico was named as one of three new sites being developed with Oracle. · source
  • 2025-09-25coverage
    El Paso Matters reported OpenAI and Oracle had confirmed their partnership on the $165 billion Project Jupiter data center in Santa Teresa as part of the Stargate initiative, with $50 billion planned over five years, 2,500 construction jobs, and 750 permanent jobs. · source
  • 2026-03-01public-comment
    Food and Water Watch reported that community members submitted over 7,000 comments to the New Mexico Environment Department regarding Project Jupiter's initial proposed gas plant (March 2026). · source
  • 2026-05-07permit
    The Bureau of Land Management used emergency permitting authority to fast-track a construction review of the Green Chile natural gas pipeline, shortening the federal environmental review from about a year to 14 days; the ~18-mile, $60 million pipeline would carry 400 million cubic feet of gas per day to serve Project Jupiter. · source
  • 2026-07-01hearing
    The New Mexico Environment Department announced it would hold a public hearing on the air permit application for Project Jupiter's microgrid in response to community opposition (July 2026). · source
  • 2026-07-28protest
    A Dona Ana County Commission meeting on Project Jupiter escalated into a physical confrontation: Commission Chair Manny Sanchez capped public comment at 30 speakers despite roughly 60 signed up; a Security Concepts guard pushed a woman to the ground, and she and two others were arrested. The guard was referred for potential felony assault charges, which prosecutors later declined to file. · source

Find the paper trail

Find the paper trail (1 filed · 11 places to look)

Permits already on file (1)

Filings we have a source for — the record, not a place to look for one.

  • 2026-05-07
    The Bureau of Land Management used emergency permitting authority to fast-track a construction review of the Green Chile natural gas pipeline, shortening the federal environmental review from about a year to 14 days; the ~18-mile, $60 million pipeline would carry 400 million cubic feet of gas per day to serve Project Jupiter. · source

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 32.350, -106.760 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in New Mexico

Cite this page: GridWatch AI, “OpenAI Stargate New Mexico”, aigridwatch.com/projects/openai-stargate-new-mexico, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).