Project dossier · Berry Hill (Pittsylvania County / Danville), Virginia

STACK Infrastructure Berry Hill megasite Approved

Up to 2,990 of the 3,528-acre Southern Virginia Megasite at Berry Hill, owned by the Danville-Pittsylvania Regional Industrial Facility Authority. Performance agreement: $73.5B minimum investment and 2,050 jobs at $80,500 average, against a stated $100B over 30 years; the county says the deal depends on Virginia keeping its data center sales-tax exemption to 2035. The county's 1991 zoning code does not mention data centers.

Key facts

Operator
Stack Infrastructure
Owner
Blue Owl / IPI Partners
Size
2,990 ac
Location
Berry Hill (Pittsylvania County / Danville), Virginia
First proposed
2026-02-20
Decided
2026-05-18
Stage today
Approved

Source
read 2026-09-05

What to do next

Next step: Approved — pivot from stopping it to a binding CBA: enforceable caps on noise, water and cost, plus a community benefit.

Build an action pack for this project →

What has happened so far (3 events)

  • 2026-02-20incentive
    The Regional Industrial Facility Authority backed an incentives deal for a data center developer at the Berry Hill megasite. · source
  • 2026-05-18vote
    The Danville-Pittsylvania Regional Industrial Facilities Authority unanimously approved STACK Infrastructure's local performance agreement: $100B over 30 years and 2,500 jobs at a minimum $80,500, with penalties if targets are missed. Economic development director Matt Rowe said the project 'is dependent upon the state honoring its commitments', including the sales-and-use tax exemption's 2035 expiry. · source
  • 2026-07-21vote
    Pittsylvania County Board of Supervisors approved a resolution supporting the campus over resident objections that industrial siting decisions were being made before the comprehensive plan and without public access to the RIFA and IDA strategy reports. Chairman Robert Tucker: 'four to five hundred million dollars of revenue' moving through the economy. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

  • Virginia DEQThe program page: which permits this state requires, and the office that issues them.
  • Search Virginia DEQ for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 36.550, -79.530 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Virginia

Cite this page: GridWatch AI, “STACK Infrastructure Berry Hill megasite”, aigridwatch.com/projects/stack-berry-hill-pittsylvania-va, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.