Talen Energy Montour Data Center Denied
County commissioners unanimously denied Talen Energy's request to rezone 800+ acres from agricultural to industrial for a data center plus power-plant expansion, after a grassroots group gathered ~3,000 petition signatures.
Key facts
- Operator
- Talen Energy
- Size
- 800 ac
- Location
- Montour County, Pennsylvania
- Stage today
- Denied
What to do next
Next step: Denied — watch for a re-filing or a scaled-down resubmission; ask the clerk to add you to the notification list.
What has happened so far (13 events)
- 2024-11-01ruling
FERC rejected a proposed interconnection service agreement among PJM, PPL Electric, and Talen that would have increased the load Talen could transfer directly from the Susquehanna nuclear plant to its co-located Amazon data center campus. · source - 2025-06-01utility
Talen Energy expanded its Amazon Web Services partnership with a new long-term agreement to supply up to 1,920 MWe from its Susquehanna nuclear plant through 2042, part of Talen's broader co-location strategy for AI data centers in Pennsylvania. · source - 2025-08-01announcement
Concerned Citizens of Montour County formed with four members after Talen's rezoning request became public; its first town hall days later drew about 120 people. · source - 2025-08-18filing
Talen Energy submitted a rezoning petition to Montour County covering roughly 870 acres in Anthony and Derry Townships, seeking to change land from agricultural to industrial near its Montour Steam Electric Station for a data center and power-plant expansion. · source - 2025-11-19hearing
The Montour County Planning Commission voted to recommend against Talen Energy's request to rezone roughly 870 acres of agricultural land to industrial. · source - 2026-01-23hearing
Montour County commissioners held an all-day public hearing at First Baptist Church of Danville on Talen's rezoning request; residents wearing red 'Say No Industrial Rezoning' shirts testified about farmland loss, water use, noise, and land impact. · source - 2026-01-23public-comment
Concerned Citizens of Montour County delivered a petition signed by about 3,000 residents opposing the rezoning, roughly twice the population of the township and more than voted there in the 2024 election. · source - 2026-02-10denial
Montour County's three commissioners voted unanimously to deny Talen Energy's rezoning request; Chair Rebecca Dressler said Talen had not met its burden of proving the project would benefit the community and that no evidence showed benefits outweighed foreseeable public harms. · source - 2026-02-10coverage
Talen Energy responded saying it remains committed to pursuing a data center in Montour County and would 'listen, incorporate feedback from the Commissioners, engage with the community, and refine our plans.' · source - 2026-03-30report
Civil Eats profiled the Montour County fight as a case study of a small farm county organizing successfully against a hyperscale data center and power-plant expansion. · source - 2026-04-14public-comment
Montour County held a public hearing on proposed amendments to its data center ordinance, including new height and setback distance requirements. · source - 2026-04-28ruling
Montour County commissioners unanimously approved amended data center ordinance provisions establishing new height and setback requirements for any future data center development. · source - 2026-08-18moratorium
Governor Josh Shapiro signed an executive order restricting data center development in Pennsylvania, eliminating fast-tracked permitting and formalizing GRID Standards requiring community engagement, energy-affordability protections, and environmental standards for developers seeking state support. · source
Find the paper trail
Find the paper trail (0 filed · 12 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Pennsylvania DEPThe program page: which permits this state requires, and the office that issues them.
- DEP Data Center Permit Tracker (the only state register built for data centers — it already feeds this tracker)Searchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Board of Commissioners agendas & packetsThe meeting packet carries the staff report, site plan and conditions — verified page for this locality.
- Search Montour County planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Montour County property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Pennsylvania Public Utility Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Recent news
Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 1 headline archived.
Around here
- Montour County community briefing — Expiredterm ran to 2026-04-30
- Pennsylvania briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Pennsylvania
- 4-3 Salem Township Data Center — Salem Township (Luzerne County) Rumored
- 900 Conshohocken Road data center (former Cleveland-Cliffs steel mill) — Plymouth Township (Montgomery County) Awaiting decision
- AWS Berwick — Berwick Under construction
- AWS Falls Township campus (Keystone Trade Center) — Falls Township (Bucks County) Approved
- AWS Salem Township campus (Susquehanna nuclear plant) — Salem Township (Luzerne County) Under construction
Cite this page: GridWatch AI, “Talen Energy Montour Data Center”, aigridwatch.com/projects/talen-montour-pa, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).