CyrusOne Fairfield Under construction
$1.5B, 760MW campus with 3 buildings in Fairfield, Texas. Under construction.
Key facts
- Operator
- CyrusOne
- Size
- 760 MW
- Location
- Fairfield (Freestone County), Texas
- Stage today
- Under construction
What to do next
Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.
What has happened so far (9 events)
- 2025-12-03incentive
Freestone County Commissioners held a public hearing and unanimously approved Reinvestment Zone Number 12 (C1 Freestone, LLC Data Center, a CyrusOne affiliate) on 507 acres near the Calpine plant, with a minimum $600 million initial improvement and a 10-year, $850,000/year payment-in-lieu-of-taxes agreement. · source - 2026-02-09announcement
Constellation's Calpine unit and CyrusOne announced a Powered Land Capabilities agreement supplying 380MW for Phase 1 of a new data center adjacent to the Freestone Energy Center, with an exclusive option for an additional 380MW in Phase 2 (760MW total). · source - 2026-05-13public-comment
A public notice regarding the data center project and upcoming county hearing was published in the Freestone County Times. · source - 2026-05-25protest
A Change.org petition titled "Ban Data Centers in Freestone County" was started, citing water, noise and light pollution, rising power costs, and health/traffic impacts; it drew hundreds of signatures ahead of the county's June hearings. · source - 2026-06-03public-comment
A Freestone County Commissioners Court meeting drew an overflow crowd (relocated to the District Courtroom) with 15+ residents raising concerns about permanent water loss, noise, health effects, and lack of transparency; resident Toni Abram asked for a 1-2 year pause, and the court scheduled a special meeting for June 10 and a public hearing for June 17. · source - 2026-06-04construction
CyrusOne held a groundbreaking ceremony for its Freestone County data center campus with County Judge Lloyd Lane, Fairfield Mayor Bobby Nichols, Calpine, and contractor Rogers-O'Brien Construction. · source - 2026-06-10hearing
A special Freestone County Commissioners Court meeting was held at which CyrusOne presented information addressing resident concerns, citing a closed-loop water system (~1,000 gallons/day per building), 45-55 decibel noise levels, about 40 jobs per building, and a 2030 carbon-neutral goal. · source - 2026-06-17withdrawal
At a public hearing on a proposed Phase 2 tax abatement, roughly 30 residents voiced opposition over noise, water pollution, utility bills, and transparency; CyrusOne subsequently rescinded its tax abatement request for Phase 2, and County Judge Lloyd Lane said the abatement agreement had been the county's only leverage over the project. · source - 2026-08-03filing
CyrusOne filed permits with the Texas Department of Licensing and Regulation for a three-building, $1.5 billion, 760MW data center campus (buildings DFW20A, DFW20B, DFW20C) on FM 488 in Fairfield, targeting completion by the end of August 2027. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Texas TCEQ — Air Permits DivisionThe program page: which permits this state requires, and the office that issues them.
- TCEQ Central RegistrySearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Fairfield (Freestone County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Fairfield (Freestone County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- ERCOT (Texas) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Public Utility Commission of Texas — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Texas briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Texas
- Aligned Data Centers Hale County — Hale County Under construction
- Amazon Floydada campus — Floydada (Floyd County) In review
- Amazon Fort Stockton campus — Fort Stockton (Pecos County) Under construction
- BCG Cedar Creek Campus — Cedar Creek (Bastrop County) Awaiting decision
- Black Mountain Energy Fort Worth — Fort Worth Approved
Cite this page: GridWatch AI, “CyrusOne Fairfield”, aigridwatch.com/projects/cyrusone-fairfield-tx, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.