Energence Utah Digital Infrastructure Campus In review
Massive 5,046-acre multi-use campus with 475-acre data center area (expandable to 1,000+ acres), 200-acre energy center, and ~1,440 acres of solar. Targets 100 MW by Year 2, 700 MW by Year 4, up to 1.2 GW firm / 1.9 GW total by Year 6. Senmiao Technology (NASDAQ: AIHS) entered a non-binding LOI for $5M staged investment for 51% equity in Energence Utah. Campus already has active conditional-use permits and 100,000 MMBTU/day gas commitment. Very early stage (LOI, not binding) and highly speculative given micro-cap sponsor.
Key facts
- Operator
- Senmiao Technology / Energence Utah LLC
- Owner
- Energence Utah LLC
- Filing LLC
- Energence Utah LLC
- Size
- 1,200 MW
- Acres
- 5,046
- Location
- Duchesne County, Utah
- First proposed
- 2026-08-11
- Stage today
- In review
Source
read 2026-08-14
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (4 events)
- 2026-03-20incentive
Utah Inland Port Authority Board officially adopted the 2,780-acre Black Gold Project Area in Duchesne County and Roosevelt City, creating an economic development zone that the Energence Utah campus would later cite as its location. · source - 2026-08-11announcement
Senmiao Technology enters LOI for $5M investment for 51% stake in Energence Utah; 100 MW targeted in initial 2-year phase. · source - 2026-08-12coverage
Pulse 2.0 reported additional details from the LOI: the 5,046-acre campus already holds active conditional-use permits for the data campus, gas generation, energy storage, and solar PV, and has secured an initial natural gas commitment of 100,000 MMBTU per day, with Elio Energy Group serving as the development services provider. · source - 2026-08-14filing
Senmiao Technology filed its 10-Q with the SEC disclosing that starting in 2026 the company began evaluating expansion into AI infrastructure, appointed David Nichols as strategic advisor for power infrastructure and capital formation, and in July 2026 formed Nebula Matrix AI LLC (90% owned) with Constant Energy Construction Corp. to develop AI data centers in the U.S. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Utah DEQ — Division of Air QualityThe program page: which permits this state requires, and the office that issues them.
- Search Utah DEQ — Division of Air Quality for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Duchesne County planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Duchesne County property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Utah Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 40.160, -110.400 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Utah briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Utah
- Meta Eagle Mountain — Eagle Mountain, 86 mi
- QTS Eagle Mountain — Eagle Mountain, 86 mi Under construction
- Stratos — Box Elder County (near Brigham City), 126 mi In review
- Antelope Data Campus (Project Antelope) — Iron County (near Cedar City), 223 mi Approved
- Valar Atomics Orangeville SMR — Orangeville (Emery County)
Cite this page: GridWatch AI, “Energence Utah Digital Infrastructure Campus”, aigridwatch.com/projects/energence-utah-duchesne-county, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.