Meta Eagle Mountain
Chip types: B300. Epoch AI estimates ~133 MW.
Key facts
- Operator
- Meta
- Owner
- Meta
- Size
- 133 MW
- Location
- Eagle Mountain, Utah
- Stage today
Source
read 2026-08-14
What to do next
Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.
What has happened so far (11 events)
- 2018-05-30announcement
Facebook announced a $750 million, 970,000-square-foot data center campus on approximately 500 acres in Eagle Mountain, with Gov. Gary Herbert and state officials present; five taxing entities ratified a $150 million tax incentive package over 20 years for Phase 1. · source - 2018-06-02coverage
Utah Public Radio reported Facebook chose Eagle Mountain for renewable energy availability, local workforce, and community support; the company had invested approximately $100 million in infrastructure to the site. · source - 2019-12-11announcement
Facebook announced Phase 2, adding 500,000 square feet to the campus and raising total investment to over $1 billion; a separate tax increment financing deal returned approximately $60 million to Facebook with $6.6 million allocated to Eagle Mountain's Redevelopment Agency for affordable housing. · source - 2021-02-11coverage
Deseret News reported Facebook's Eagle Mountain campus had logged over 4 million construction work hours and used over 12,000 tons of steel and 100,000 cubic yards of concrete, with potential tax relief across all five phases totaling $750 million over 40 years. · source - 2021-02-12announcement
Facebook announced a further 900,000-square-foot expansion with two new buildings, bringing planned campus total to five buildings with approximately 1,500 workers at peak construction. · source - 2021-03-08announcement
EDCUtah, Eagle Mountain, and the Governor's Office of Economic Development jointly announced 'Project Steeplechase II,' the 900,000-square-foot, two-building expansion powered by 100% renewable energy from over 600 MW of new solar capacity on Utah's grid. · source - 2021-07-14operational
Facebook's Eagle Mountain data center began serving traffic, marking the first phase as operational; the company reported over $1 billion invested, 1,250 workers at peak construction, and approximately $2 million in community grants since 2018 groundbreaking. · source - 2021-10-04coverage
Deseret News reported the first phase of Facebook's Eagle Mountain data center went live in July 2021 as Phase 2 construction continued, with over 1,200 workers at peak and plans for five total buildings on the 500-acre site. · source - 2022-09-30announcement
Meta announced Phase 3, adding approximately 2 million square feet via two new buildings to bring the campus to 4.5 million square feet across seven data centers, raising total investment to $1.5 billion; the company also announced a $200,000 grant for the Hobble Creek Flow Restoration Project. · source - 2022-09-30environmental
Meta committed to funding water restoration projects equaling 200% of the Eagle Mountain facility's water consumption into the Provo River watershed, including 416 million gallons annually from an existing Provo River project and 467 million gallons from the new Hobble Creek project. · source - 2022-10-03coverage
W.Media reported Meta's Phase 3 expansion would add two buildings totaling approximately 2 million square feet to the existing 2.4 million square feet, with Meta having invested $120 million in infrastructure upgrades (roads, electricity) before construction began. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Utah DEQ — Division of Air QualityThe program page: which permits this state requires, and the office that issues them.
- Search Utah DEQ — Division of Air Quality for this projectsearchThis state publishes no searchable permit database, so a written records request to the agency is the reliable route. Use this search only to find the right office.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Eagle Mountain planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Eagle Mountain property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- No organised market covers this statenoteThere is no public queue to read. The record is the utility's integrated resource plan and its filings at the PUC — plus FERC eLibrary for anything federally docketed.
- Utah Public Service Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 40.310, -112.010 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Recent news
- Data centers got tax breaks. Homeowners were asked to pay triple. Here’s how Eagle Mountain’s tax fight shook out.
- Utah Residents Protest Kevin O’Leary’s Proposed AI Data Center Campus
- Kevin O'Leary's Utah data center — 3 times the size of Manhattan — sparks 'Shame!' chants from furious residents
Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 3 headlines archived.
Around here
- Utah briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Utah
- QTS Eagle Mountain — Eagle Mountain, 0 mi Under construction
- Stratos — Box Elder County (near Brigham City), 83 mi In review
- Energence Utah Digital Infrastructure Campus — Duchesne County, 86 mi In review
- Antelope Data Campus (Project Antelope) — Iron County (near Cedar City), 190 mi Approved
- Valar Atomics Orangeville SMR — Orangeville (Emery County)
Cite this page: GridWatch AI, “Meta Eagle Mountain”, aigridwatch.com/projects/meta-eagle-mountain, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).