Microsoft La Porte Under construction
$1B, 245,000 sq ft data center in La Porte, Indiana. Under construction.
Key facts
- Operator
- Microsoft
- Owner
- Microsoft
- Location
- La Porte, Indiana
- Stage today
- Under construction
What to do next
Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.
What has happened so far (12 events)
- 2024-06-04announcement
Gov. Eric Holcomb and Microsoft announced a $1 billion investment to build a 245,000 sq ft data center on 489 acres at Radius Industrial Park in La Porte, Indiana, projected to create up to 200 jobs by 2032. · source - 2024-06-04incentive
The Indiana Economic Development Corporation committed a 35-year (extendable to 45-year) data center sales tax credit tied to a minimum $1 billion capital investment at the La Porte site. · source - 2026-01-13incentive
Microsoft President Brad Smith unveiled a national Community-First AI Infrastructure Plan pledging Microsoft would no longer seek local property tax abatements — a policy shift that prompted renegotiation of the La Porte tax deal. · source - 2026-03-01construction
Microsoft began site preparation work on the La Porte campus, with the first three data center buildings under construction through end of 2027 and full buildout expected by 2029. · source - 2026-03-04incentive
La Porte and the school corporation approved a revised tax agreement in which Microsoft will pay its full property tax obligation, with 15% dedicated to La Porte Community School Corporation for 20 years. · source - 2026-04-13hearing
La Porte City Council held a hearing on annexing more than 1,000 acres of farmland adjacent to the existing Microsoft site for a second data center campus; officials cited a lack of transparency while some residents supported the jobs. · source - 2026-04-21public-comment
Microsoft held a community information session at the La Porte Civic Auditorium attended by hundreds; residents raised concerns about water usage, noise (including low-frequency vibrations), lighting/visual impact, and being excluded from earlier decisions. · source - 2026-05-06vote
LaPorte County commissioners voted unanimously to advance a new data center ordinance setting setbacks, noise limits, and water-usage caps and restricting data centers to industrial-zoned land. · source - 2026-05-13rezoning
The La Porte Plan Commission approved rezoning roughly 1,300 acres near Boyd Boulevard and U.S. 35 from agricultural to manufacturing use for Microsoft expansion. · source - 2026-05-18rezoning
La Porte Common Council unanimously approved final annexation and rezoning of more than 1,000 additional acres in Pleasant Township for light industrial/manufacturing use, nearly tripling the planned Microsoft campus to support up to 17 total data center buildings. · source - 2026-06-17construction
Microsoft held a groundbreaking ceremony for the $1 billion La Porte campus expansion; Mayor Tom Dermody called it a defining moment for the community. · source - 2026-06-17utility
NIPSCO confirmed it is working directly with Microsoft to supply power for the expanded La Porte campus, including a new substation as part of the first construction phase. · source
Find the paper trail
Find the paper trail (0 filed · 12 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Indiana IDEM — Office of Air QualityThe program page: which permits this state requires, and the office that issues them.
- IDEM Virtual File CabinetSearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search La Porte planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search La Porte property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- MISO (Midwest & Gulf) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Indiana Utility Regulatory Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Indiana briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Indiana
- AWS Northern Indiana expansion (New Carlisle) — New Carlisle (St. Joseph County)
- Abei Energy data center proposal (rezoning request) — Starke County Blocked by ban
- Anthropic-Amazon New Carlisle — New Carlisle
- Cloverdale Solar Farm (EnergyRe) — Putnam County Withdrawn
- DC Blox Warren Township (Thunderbird Commerce Center) — Warren Township (Indianapolis) / Irvington Approved
Cite this page: GridWatch AI, “Microsoft La Porte”, aigridwatch.com/projects/microsoft-la-porte-in, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).