Matrix Data Center Campus Under construction
$18.7B, 1,677-acre, 3GW net-zero AI campus on former Thermo lignite mine land. Phase I: 390 acres/800MW across 8 buildings; Phase II adds geothermal microgrid by 2027.
Key facts
- Operator
- MSB Global Services
- Size
- 800 MW
- Acres
- 1,677
- Location
- Sulphur Springs (Hopkins County), Texas
- Stage today
- Under construction
What to do next
Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.
What has happened so far (16 events)
- 2019-01-01filing
Vistra/Luminant Mining conveyed roughly 5,000 acres of the former Thermo lignite mine to the City of Sulphur Springs; the deed included a restrictive covenant barring power generation or storage on the land. · source - 2025-02-01construction
Phase I construction begins on the Matrix Data Center Campus: site grading, Trinity Road work, and utility infrastructure ahead of the eight-building, 800MW first phase. · source - 2025-06-13construction
MSB Global holds official groundbreaking ceremony for the Matrix Data Center Campus, an 1,677-acre, up to 3GW, $18.7B hyperscale AI campus billed as a public-private partnership with the City of Sulphur Springs and Hopkins County. · source - 2025-09-30filing
Vistra sends Sulphur Springs a cease-and-desist letter asserting the 2019 deed restrictive covenant bars on-site power generation/storage needed for the data center campus. · source - 2025-10-15lawsuit
City of Sulphur Springs sues Vistra and Luminant Mining, arguing the restrictive covenant is unenforceable and against public policy; Vistra counters the covenant was known to the city. · source - 2025-11-01filing
Texas AG Ken Paxton files an amicus brief supporting the City, revealing an Antitrust Division investigation into Luminant for inserting the same power-generation restrictive covenant into roughly 150 deeds across 18 Texas counties, calling it an attempt to improperly enrich Luminant by nearly $15 billion. · source - 2025-11-25filing
Vistra and Luminant file their First Amended Answer and Counterclaims in Hopkins County (Cause No. CV45943), escalating the legal battle over the data center site. · source - 2026-01-21hearing
Hopkins County District Court hearing; City Manager Marc Maxwell is subpoenaed by Vistra counsel and testifies; residents publicly press officials for answers on the project. · source - 2026-02-10ruling
Judge Dan Moore denies a major City motion and issues a temporary injunction freezing new construction/development on the ~5,000-acre site pending trial, effectively halting power-system construction. · source - 2026-04-15lawsuit
Resident Jack Curtis files suit alleging the City Council violated the Texas Open Meetings Act by concealing data-center deal details in council minutes/agendas. · source - 2026-05-06vote
Sulphur Springs City Council authorizes $1.2 million in legal funding for the ongoing data-center litigation; residents protest the spending at the meeting. · source - 2026-05-06protest
Residents protest outside the Sulphur Springs City Council meeting over the $1.2 million legal-cost allocation, citing lack of transparency. · source - 2026-06-03announcement
At a packed City Council meeting, Mayor Tyler Law announces a new developer will take over the Matrix Data Center Campus, with original developer MSB Global being phased out amid the legal battles. · source - 2026-07-07hearing
Judge Dan Moore hears over three hours of arguments on Vistra Rule 91a motion to dismiss 6 of 11 counts, focused on fraud allegations and when the city became aware of the deed restrictive covenant; no ruling issued. · source - 2026-07-18protest
Sulphur Springs residents hold a peaceful demonstration against the data center as part of a coordinated nationwide National Day of Protest organized by advocacy group Humans First. · source - 2026-08-01coverage
Heatmap News reports the trial original September 2026 date has been cancelled/pushed back, with the case now likely heading to trial in 2027. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Texas TCEQ — Air Permits DivisionThe program page: which permits this state requires, and the office that issues them.
- TCEQ Central RegistrySearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Sulphur Springs (Hopkins County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Sulphur Springs (Hopkins County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- ERCOT (Texas) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Public Utility Commission of Texas — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Texas briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Texas
- Aligned Data Centers Hale County — Hale County Under construction
- Amazon Floydada campus — Floydada (Floyd County) In review
- Amazon Fort Stockton campus — Fort Stockton (Pecos County) Under construction
- BCG Cedar Creek Campus — Cedar Creek (Bastrop County) Awaiting decision
- Black Mountain Energy Fort Worth — Fort Worth Approved
Cite this page: GridWatch AI, “Matrix Data Center Campus”, aigridwatch.com/projects/msb-sulphur-springs-tx, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).