Project Riverjump (Marion) Withdrawn
Code-named hyperscale data center proposed for the west side of the City of Marion, the county seat. Because Marion is incorporated, the county's 24-month moratorium (Ordinance 4-2026) never applied to it. Rumors of a data center west of Marion near Central Indiana Ethanol circulated from January 2026; Mayor Ronald Morrell Jr. said then that no ordinance or vote was scheduled. In late August 2026, citing public feedback in person and online, Morrell said he would not pursue or support data center development in Marion under his administration. The developer and end user were never publicly identified; no application appears in the public record.
Key facts
- Location
- Marion (Grant County), Indiana
- Decided
- 2026-08-27
- Stage today
- Withdrawn
Source
read 2026-09-02
What to do next
Next step: Withdrawn — confirm it is dead in the record and watch for the same site resurfacing under a new name or LLC.
What has happened so far (4 events)
- 2026-01-20coverage
Chronicle-Tribune reported rumors of data center construction west of Marion near Central Indiana Ethanol, traced to a satirical Facebook post; Mayor Ronald Morrell said there was 'currently no ordinance or vote scheduled related to a data center' and Councilman Mike Cline declined to comment on rumors. · source - 2026-02-23protest
Marion resident Molly Earley launched a change.org petition, 'Ban new data centers on farmland and in towns', addressed to the Grant County commissioners and the Area Plan Commission; it passed 2,000 signatures by September 2026. · source - 2026-08-27withdrawal
Chronicle-Tribune reported the City of Marion is no longer moving forward with Project Riverjump, a hyperscale data center planned for the city's west side; Mayor Ronald Morrell Jr. said that based on citizen feedback he 'will not be pursuing or supporting data center development in the City of Marion under my administration.' · source - 2026-09-02coverage
Chronicle-Tribune columnist Laura Mack credited public outcry for the project's end and quoted the mayor's statement that 'the message I have received from our citizens regarding data center development has been clear.' · source
Find the paper trail
Find the paper trail (0 filed · 12 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Indiana IDEM — Office of Air QualityThe program page: which permits this state requires, and the office that issues them.
- IDEM Virtual File CabinetSearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Marion (Grant County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Marion (Grant County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- MISO (Midwest & Gulf) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- PJM Interconnection (Mid-Atlantic, Ohio Valley) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Indiana Utility Regulatory Commission — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 40.556, -85.700 — search that point with a 5-mile radius.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Grant County community briefing — Enactedexpires 2028-03-16
- Indiana briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Indiana
- Recore Digital AI data center inquiry — Grant County, 4 mi Rumored
- Decennial Group Akron Data Center Campus (proposed) — Fulton County (Akron), 37 mi Blocked by ban
- Google Fort Wayne — Fort Wayne, 44 mi
- Meta Lebanon / LEAP Data Center Campus — Boone County, 53 mi Proposed
- DC Blox Warren Township (Thunderbird Commerce Center) — Warren Township (Indianapolis) / Irvington, 57 mi Approved
Cite this page: GridWatch AI, “Project Riverjump (Marion)”, aigridwatch.com/projects/project-riverjump-marion-in, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).