Project dossier · Boone County, Indiana

Meta Lebanon / LEAP Data Center Campus Proposed

1500-acre, 1GW, $10B+ Meta campus at the LEAP Lebanon Innovation District. Multiple sources (WISH-TV, WRTV, Data Center Dynamics, IndyStar) place this site on land annexed into the City of Lebanon as part of the state-sponsored LEAP district -- NOT unincorporated Boone County and NOT the Town of Advance. This conflicts with the task baseline description citing the Town of Advance; flagging for the tracker maintainer to reconcile (see research_notes). Either way, all reporting agrees this project is exempt from the county's unincorporated-land moratorium. First proposed publicly around Nov 2024 (~$800M), then expanded to the current $10B/1GW scope announced Feb 2026; groundbreaking construction reported ongoing through mid-2026 with resident complaints about light/noise pollution.

Key facts

Operator
Meta
Tenant
Meta
Size
1,000 MW
Acres
1,500
Location
Boone County, Indiana
First proposed
2026-02-11
Stage today
Proposed

Source
read 2026-09-02

What to do next

Next step: Early stage. File a public-records request for the application and site plan.

Build an action pack for this project →

What has happened so far (4 events)

  • 2024-11-25announced
    Meta proposes ~$800 million data center in Lebanon, Indiana. · source
  • 2026-02-11announced
    Meta officially announces expanded $10B, 1GW data center campus at LEAP District in Lebanon. · source
  • 2026-06-15moratorium
    Boone County passes a 1-year moratorium on new data centers in unincorporated county land; county officials and press confirm this does not affect the Meta LEAP/Lebanon project because it sits on annexed City of Lebanon land, not unincorporated county land. · source
  • 2026-07-08community-impact
    IndyStar reports ongoing construction disruption for neighbors (light pollution, noise) during Meta campus build-out. · source

Find the paper trail

Find the paper trail (0 filed · 13 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 40.049, -86.464 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Recent news

16 stories tracked since 2025-08-15 across 14 outlets. 13× Local officials are moving to pause or block the project. 1× Noise from the facility is drawing resident complaints. Most recent: “Oklahoma Worker, 33, Killed by Pickup Truck at Meta's Lebanon Data Center Site” (hoodline.com, 2026-09-15).

+4 more on the story tracker.

Automated news aggregation, not human-verified — follow each link to the original outlet. Part of the story tracker, 16 headlines archived.

Around here

Other tracked projects in Indiana

Cite this page: GridWatch AI, “Meta Lebanon / LEAP Data Center Campus”, aigridwatch.com/projects/meta-leap-lebanon-in, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).