QTS / Lancium Turkey TX In review
$10B+ GW-scale data center campus in Turkey, Texas.
Key facts
- Operator
- QTS / Lancium
- Location
- Turkey (Hall County), Texas
- Stage today
- In review
What to do next
Next step: An application is in the record. Ask the planning office for the next hearing date and request formal notice.
What has happened so far (9 events)
- 2025-06-05public-comment
Lancium held a town hall in Turkey, Texas drawing dozens of residents for a three-and-a-half-hour discussion; CEO Michael McNamara answered questions. · source - 2025-06-09incentive
Hall County Commissioners Court unanimously approved a property tax abatement for Lancium Clean Campus: 75% abatement phased across 10 annual increments, below the 85% Lancium had originally requested. · source - 2026-07-13announcement
QTS and Lancium formally announced a joint $10B+ data center campus on Lancium Clean Campus near Turkey: up to 11 buildings across ~465 acres, 1GW grid connection, Lancium supplying dedicated solar/battery and funding 100% of energy infrastructure; closed-loop cooling designed to use no water. · source - 2026-07-13coverage
Trade and local press (DatacenterDynamics, Baxtel, ABC7 Amarillo) covered the QTS/Lancium Hall County announcement, reiterating the 11-building, 465-acre, 1GW, $10B campus figures. · source - 2026-07-17coverage
NewsChannel 10 reported on the project, quoting Hall County Judge Ray Powell and noting water would come from onsite wells rather than Turkey municipal supply. · source - 2026-08-05moratorium
Gov. Abbott ordered PUC of Texas and ERCOT to audit every data center in the interconnection queue (~1,800 projects) before further grid-connection approvals, affecting all pending Texas data center interconnections including large-load projects like Lancium Turkey campus. · source - 2026-08-10coverage
Lancium issued a statement supporting Gov. Abbott transparency/accountability push, with CEO McNamara pledging verified power/water reporting, full grid-upgrade funding, and closed-loop cooling. · source - 2026-08-12public-comment
ABC7 Amarillo reported Hall County residents raising concerns about water usage and housing-cost strain; QTS responded closed-loop buildings would use ~50,000 gallons/month each (about five single-family homes) and most workers housed on-site. · source - 2026-08-14public-comment
QTS and Lancium held a community engagement meeting at Valley High School (5:30-7:30 PM) to address resident concerns on tax revenue, school/workforce partnerships, and infrastructure support. · source
Find the paper trail
Find the paper trail (0 filed · 11 places to look)
State environmental permits
Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.
- Texas TCEQ — Air Permits DivisionThe program page: which permits this state requires, and the office that issues them.
- TCEQ Central RegistrySearchable public filings — search the operator, the shell LLC on the deed, and the address.
County & town filings
The rezoning application, site plan, traffic and noise studies, staff report and every revision.
- Search Turkey (Hall County) planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
- Search Turkey (Hall County) property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.
Utility & grid records
The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.
- ERCOT (Texas) — interconnection queueRequested megawatts, queue position and target in-service date. The MW here is the real number; the one at the town meeting is often phase one.
- Public Utility Commission of Texas — docket searchSpecial contracts, large-load tariffs and rate cases are docketed here. Testimony and exhibits are public, and are usually more candid than the press release.
- FERC eLibraryFederal filings: transmission agreements, interconnection service agreements, and co-location disputes.
- Search the serving utility for a will-serve lettersearchThe will-serve or load-service letter is the utility's own written commitment. Ask the utility and the PUC for it by name — it is frequently the first document to exist.
Federal databases
Works anywhere, and covers the operator's record at its other sites.
- EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
- EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
- EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.
These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.
Around here
- Texas briefing — rates, grid carbon, PUC contacts.
Other tracked projects in Texas
- Aligned Data Centers Hale County — Hale County Under construction
- Amazon Floydada campus — Floydada (Floyd County) In review
- Amazon Fort Stockton campus — Fort Stockton (Pecos County) Under construction
- BCG Cedar Creek Campus — Cedar Creek (Bastrop County) Awaiting decision
- Black Mountain Energy Fort Worth — Fort Worth Approved
Cite this page: GridWatch AI, “QTS / Lancium Turkey TX”, aigridwatch.com/projects/qts-lancium-turkey-tx, retrieved 2026-10-11.
As of August 2026 (2m ago) · changes weekly — re-check before citing
A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.
Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).