Project dossier · Canton (Madison County), Mississippi

Amazon Madison Mega Site Operating

Part of Project Rainier. Chip types: Trainium2. Epoch AI estimates ~284 MW.

Key facts

Operator
Amazon
Owner
Amazon
Tenant
Anthropic
Size
284 MW
Location
Canton (Madison County), Mississippi
Stage today
Operating

Source
read 2026-08-14

What to do next

Next step: Already operating — the leverage now is enforcement: noise and water conditions, tax revenue tracking, and any expansion filing, which reopens the record.

Build an action pack for this project →

What has happened so far (8 events)

  • 2024-01-25announcement
    Amazon Web Services announced plans to invest $10 billion to build multiple data center complexes in two Madison County industrial parks, creating at least 1,000 high-paying jobs, with a 10-year, 100% corporate income tax exemption incentive package. · source
  • 2024-05-20construction
    AWS held a ceremonial groundbreaking at the Madison County Mega Site spec building, attended by Governor Tate Reeves, Senators Roger Wicker and Cindy Hyde-Smith, and Representatives Michael Guest and Bennie Thompson. · source
  • 2025-10-29operational
    AWS's Project Rainier — the AI training cluster powering Anthropic's Claude, spread across Pennsylvania, Indiana, and Mississippi — was reported operational, with its Mississippi campus near Canton in Madison County cited at more than 350 MW of IT capacity and set to ramp past 1 GW. · source
  • 2026-02-19coverage
    Residents of the Idlebriar subdivision in Canton, next to the Amazon data center construction site, reported two years of construction dust, noise and traffic, with one resident's teenage daughter having multiple ER visits for asthma flare-ups the prior year, while the Madison County Economic Development Authority said it lacks funds to buy out the subdivision. · source
  • 2026-04-09announcement
    Governor Tate Reeves and Amazon announced an additional $11 billion expansion of Madison County data center operations (700 new jobs) plus a $1 billion facility in Clinton/Hinds County (100 jobs), bringing Amazon total Mississippi investment commitment to $25 billion and over 2,000 jobs. · source
  • 2026-04-10environmental
    Coverage noted Amazon's environmental commitments: Canton will use recycled water for cooling, the Ridgeland campus will draw groundwater only 9% of the time, and the Clinton facility will operate without water, alongside plans for over 800 diesel generators across the Madison County campuses. · source
  • 2026-04-22coverage
    Canton residents described construction dust, noise and pollution fears; Madison County constable Johnny Sims said construction dust had worsened his teenage daughter's asthma, and Amazon stated it is committed to being a responsible community partner. · source
  • 2026-06-09coverage
    Of Amazon four announced Mississippi data center facilities, the Canton campus in Madison County was reported as the one currently operating, with more than 700 diesel generators planned across the two Madison County campuses and the Canton facility set to transition to 100% recycled wastewater for cooling by 2027. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site. This project's locality centres on 32.610, -90.030 — search that point with a 5-mile radius.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Mississippi

Cite this page: GridWatch AI, “Amazon Madison Mega Site”, aigridwatch.com/projects/amazon-madison-mega-site, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).

Toolkit States Tracker Search