Project dossier · Meridian, Mississippi

Compass Datacenters Meridian Under construction

$10B, 500MW campus with 8 facilities in Meridian, Mississippi. Under construction.

Key facts

Operator
Compass Datacenters
Size
500 MW
Location
Meridian, Mississippi
Stage today
Under construction

Source

What to do next

Next step: Under construction — pull the approved conditions and permits and hold the builder to them; an expansion or a new building reopens the record.

Build an action pack for this project →

What has happened so far (12 events)

  • 2025-01-01coverage
    Mississippi State University and state leaders publicly welcomed Compass Datacenters arrival in Meridian. · source
  • 2025-01-09announcement
    Compass Datacenters announced plans to build an eight-building, 500MW hyperscale campus in the I-20/59 industrial park in Lauderdale County (Meridian), representing a $10 billion investment. Gov. Reeves called it a monumental economic development win. · source
  • 2025-01-17coverage
    Meridian Star editorial credits months of closed-door discussions between EMBDC, Lauderdale County Supervisors, City of Meridian, and Mississippi Power for landing the Compass project. · source
  • 2025-01-28construction
    Compass Datacenters held its official groundbreaking ceremony near the I-20/I-59 corridor in Lauderdale County, attended by Gov. Reeves, PSC Commissioner Stamps, and Compass VP Katie Hancock. · source
  • 2025-02-01incentive
    Mississippi Development Authority certified Compass as a data center operator, granting 10-year state income/franchise tax exemptions plus sales/use tax exemption on construction materials, equipment, and software/hardware replacements. · source
  • 2025-02-07utility
    Mississippi Public Service Commission approved the special electric service contract between Mississippi Power and Compass Datacenters Jan I, LLC, clearing the way for ~500MW of supply to the campus. · source
  • 2025-02-25filing
    Mississippi Senate unanimously passed SB 3168, updating the state Data Center Enterprise incentive program (raising investment thresholds, adding an electricity tax exemption, allowing automatic 10-year extensions). · source
  • 2025-12-29coverage
    Center for Economic Accountability named Mississippi Compass Datacenters/Lauderdale County tax-break package the nation Worst Economic Development Deal of the Year for 2025, citing the length and breadth of tax exemptions versus minimal disclosed local benefit. · source
  • 2026-05-08public-comment
    Compass held a lunch and learn informational session at the MSU Riley Center; residents raised concerns about rising electricity and water bills, and Compass VP Sarah Ridgely responded the campus uses closed-loop water cooling. · source
  • 2026-07-15coverage
    Lauderdale County officials issued a statement strongly supporting the Compass project as transformational, citing 1,000+ construction jobs and hundreds of permanent jobs. · source
  • 2026-07-16hearing
    Mississippi Legislature AI Task Force held a two-day hearing on data center impacts; Compass SVP Brent Collard testified the company invested $300 million in Meridian grid infrastructure and created 6,400 long-term jobs, while other testimony raised statewide concerns about noise, air pollution, and water draw. · source
  • 2026-07-31coverage
    Compass and Meridian Community College launched Mississippi first data center workforce training program (14-week MEI Data Center Pathway) with Compass funding full-tuition scholarships for an inaugural cohort of 12 students. · source

Find the paper trail

Find the paper trail (0 filed · 11 places to look)

State environmental permits

Backup generators, water withdrawal and stormwater are permitted by the state, usually earlier and in more detail than anything filed locally.

County & town filings

The rezoning application, site plan, traffic and noise studies, staff report and every revision.

  • Search Meridian planning filingssearchPlanning departments post application files under many different names. Find the department, then ask the clerk for the application number — that number unlocks everything else.
  • Search Meridian property records / GISsearchThe parcel record names the buying LLC and the sale date, which is what ties an anonymous filing to an operator.

Utility & grid records

The electricity request is filed with the grid operator and the utility long before the town hears about it — and states the real load.

Federal databases

Works anywhere, and covers the operator's record at its other sites.

  • EPA ECHO facility searchEvery federally-reported air, water and waste permit at a facility, plus its inspection and violation history. Search by address or draw a radius around the site.
  • EPA EnvirofactsThe same underlying records, queryable by county — useful for 'what else is permitted near this site' rather than one facility.
  • EPA Facility Registry ServiceResolves the shell LLC on a permit to the facility it belongs to. Worth a look when the filing name means nothing locally.

These are places to look, not evidence that anything has been filed. Links were checked on 2026-08-21; search links are queries, not records. What to ask for.

Around here

Other tracked projects in Mississippi

Cite this page: GridWatch AI, “Compass Datacenters Meridian”, aigridwatch.com/projects/compass-meridian-ms, retrieved 2026-10-11.

As of August 2026 (2m ago) · changes weekly — re-check before citing

A working set of identified proposals a community can track, not a census — most of the country's activity is not in here yet. Pennsylvania is the exception: its rows are synced from PA DEP's own data-center permit tracker, so the state's coverage is close to complete and carries the permit trail with it. **Each row carries its own provenance.** Rows showing a verification date link to reporting or the governing body's own record and were read on that date; rows marked *unverified* have no source on record — a lead to check, not a fact to cite. **Stage is derived, not asserted.** *Hearing scheduled*, *Awaiting decision*, *Approved* and *Withdrawn* are computed from each row's milestone dates on every rebuild, so a hearing date that has passed stops reading 'scheduled'. Hearings get moved and projects re-file under new names — treat a scheduled date as the earliest to act by, and confirm with the clerk before relying on it. Leads are mined into data/project_candidates.json and promoted here only after a human reads a primary source.

Part of the data center project tracker — open data, CC BY 4.0 (JSON · CSV).