Data center moratoriums & pushback
As of September 27, 2026, this tracker lists 858 data center moratoriums and pushback actions across 49 states: 690 in force today, 83 proposed, and 858 carrying a primary source and a verification date.
Every community that pressed pause on data center development — bans, moratoria, zoning fights, and the outcomes. Each row shows where it came from and when it was last checked.
Where and when
Every tracked local action
Actions by month
Stacked by status at build time — an old month's bar can still show a color change if a row from that month later expired or was rescinded · 195 rows excluded (only a year is documented).
Deadlines in the next 90 days
Derived from documented end dates. Moratoriums are routinely extended, so treat these as the earliest a pause could end — a prompt to call the clerk, not a conclusion. Subscribe by RSS · JSON
- Lodi Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-02 (56 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Hayes Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-09 (49 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Kingsland, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-09 (49 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Saugatuck Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-11 (47 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Leavenworth County, KS: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-11 (47 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - York Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-12 (46 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading.
97 more deadlines in this window
- Massillon, OH: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-14 (44 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Hall County, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-25 (33 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Wixom, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-26 (32 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Floyd County, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-28 (30 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Mount Orab, OH: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-30 (28 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Lyon Charter Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-08-30 (28 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Hogansville, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-01 (26 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Birmingham, AL: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-03 (24 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Rockdale County, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-08 (19 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Wichita, KS: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-10 (17 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Scott County, KY: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-13 (14 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Augusta, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-19 (8 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Augusta-Richmond County, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-19 (8 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Roswell, GA: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-20 (7 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Waterford Township, MI: data center moratorium has lapsed
The moratorium's documented term ran to 2026-09-23 (4 days ago). Unless it was extended, new applications can be filed again. Confirm the current status with the clerk before relying on either reading. - Tulare County, CA: data center moratorium expires in 5 days
The documented term ends 2026-10-02. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Front Royal, VA: data center moratorium expires in 7 days
The documented term ends 2026-10-04. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Newton County, GA: data center moratorium expires in 8 days
The documented term ends 2026-10-05. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Pierce Township, OH: data center moratorium expires in 12 days
The documented term ends 2026-10-09. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Calaveras County, CA: data center moratorium expires in 12 days
The documented term ends 2026-10-09. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lake Elsinore, CA: data center moratorium expires in 12 days
The documented term ends 2026-10-09. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Bangor, ME: data center moratorium expires in 13 days
The documented term ends 2026-10-10. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Tallmadge, OH: data center moratorium expires in 13 days
The documented term ends 2026-10-10. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Palm Springs, CA: data center moratorium expires in 13 days
The documented term ends 2026-10-10. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Morgan Hill, CA: data center moratorium expires in 13 days
The documented term ends 2026-10-10. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Escondido, CA: data center moratorium expires in 15 days
The documented term ends 2026-10-12. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Vienna Township (Trumbull Co.), OH: data center moratorium expires in 19 days
The documented term ends 2026-10-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Cleveland, OH: data center moratorium expires in 19 days
The documented term ends 2026-10-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Indio, CA: data center moratorium expires in 19 days
The documented term ends 2026-10-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Mendocino County, CA: data center moratorium expires in 19 days
The documented term ends 2026-10-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Eureka, CA: data center moratorium expires in 20 days
The documented term ends 2026-10-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Plainfield, IL: data center moratorium expires in 21 days
The documented term ends 2026-10-18. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - White County, IN: data center moratorium expires in 23 days
The documented term ends 2026-10-20. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lowndes County, GA: data center moratorium expires in 28 days
The documented term ends 2026-10-25. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lowndes County, AL: data center moratorium expires in 28 days
The documented term ends 2026-10-25. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lexington (Fayette County), KY: data center moratorium expires in 34 days
The documented term ends 2026-10-31. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - West Whiteland Township, PA: data center moratorium expires in 35 days
The documented term ends 2026-11-01. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Upper Burrell Township, PA: data center moratorium expires in 36 days
The documented term ends 2026-11-02. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Smithfield Township, PA: data center moratorium expires in 36 days
The documented term ends 2026-11-02. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Charlotte, NC: data center moratorium expires in 39 days
The documented term ends 2026-11-05. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lavon, TX: data center moratorium expires in 39 days
The documented term ends 2026-11-05. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lysander (Onondaga Co.), NY: data center moratorium expires in 40 days
The documented term ends 2026-11-06. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Camden County, GA: data center moratorium expires in 40 days
The documented term ends 2026-11-06. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Johnson County, IA: data center moratorium expires in 42 days
The documented term ends 2026-11-08. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Butler Township, PA: data center moratorium expires in 42 days
The documented term ends 2026-11-08. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Riley County, KS: data center moratorium expires in 46 days
The documented term ends 2026-11-12. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Dickinson County, IA: data center moratorium expires in 46 days
The documented term ends 2026-11-12. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Springfield, MO: data center moratorium expires in 51 days
The documented term ends 2026-11-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Putnam County, IN: data center moratorium expires in 51 days
The documented term ends 2026-11-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Meridian Township, MI: data center moratorium expires in 53 days
The documented term ends 2026-11-19. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Barnes County, ND: data center moratorium expires in 53 days
The documented term ends 2026-11-19. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Minneapolis, MN: data center moratorium expires in 55 days
The documented term ends 2026-11-21. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Iron County, UT: data center moratorium expires in 56 days
The documented term ends 2026-11-22. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Washington Township (Macomb Co.), MI: data center moratorium expires in 57 days
The documented term ends 2026-11-23. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Marshalltown, IA: data center moratorium expires in 57 days
The documented term ends 2026-11-23. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Hillsboro, OR: data center moratorium expires in 58 days
The documented term ends 2026-11-24. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Bloomington, IL: data center moratorium expires in 60 days
The documented term ends 2026-11-26. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Hart, MI: data center moratorium expires in 60 days
The documented term ends 2026-11-26. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Westbrook, ME: data center moratorium expires in 62 days
The documented term ends 2026-11-28. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Gorham, ME: data center moratorium expires in 63 days
The documented term ends 2026-11-29. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Forest Park, GA: data center moratorium expires in 63 days
The documented term ends 2026-11-29. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Brunswick, ME: data center moratorium expires in 63 days
The documented term ends 2026-11-29. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Normal, IL: data center moratorium expires in 64 days
The documented term ends 2026-11-30. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - El Dorado, KS: data center moratorium expires in 64 days
The documented term ends 2026-11-30. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Scarborough, ME: data center moratorium expires in 64 days
The documented term ends 2026-11-30. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Nashville, TN: data center moratorium expires in 65 days
The documented term ends 2026-12-01. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Skagit County, WA: data center moratorium expires in 65 days
The documented term ends 2026-12-01. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Boulder County, CO: data center moratorium expires in 66 days
The documented term ends 2026-12-02. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Braceville Township, OH: data center moratorium expires in 66 days
The documented term ends 2026-12-02. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Johnson City, TN: data center moratorium expires in 67 days
The documented term ends 2026-12-03. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Hazle Township, PA: data center moratorium expires in 69 days
The documented term ends 2026-12-05. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Little Britain Township, PA: data center moratorium expires in 70 days
The documented term ends 2026-12-06. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lake County, FL: data center moratorium expires in 71 days
The documented term ends 2026-12-07. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Box Elder County, UT: data center moratorium expires in 71 days
The documented term ends 2026-12-07. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Center Township, PA: data center moratorium expires in 71 days
The documented term ends 2026-12-07. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Green Charter Township, MI: data center moratorium expires in 73 days
The documented term ends 2026-12-09. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Howland Township, OH: data center moratorium expires in 74 days
The documented term ends 2026-12-10. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Milford, UT: data center moratorium expires in 77 days
The documented term ends 2026-12-13. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Brookville, PA: data center moratorium expires in 78 days
The documented term ends 2026-12-14. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Cumberland County, NC: data center moratorium expires in 79 days
The documented term ends 2026-12-15. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Starke County, IN: data center moratorium expires in 79 days
The documented term ends 2026-12-15. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Lycoming County, PA: data center moratorium expires in 79 days
The documented term ends 2026-12-15. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Spokane County, WA: data center moratorium expires in 79 days
The documented term ends 2026-12-15. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Fort Payne, AL: data center moratorium expires in 80 days
The documented term ends 2026-12-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Butler County, OH: data center moratorium expires in 80 days
The documented term ends 2026-12-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Archuleta County, CO: data center moratorium expires in 80 days
The documented term ends 2026-12-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Webster County, MO: data center moratorium expires in 80 days
The documented term ends 2026-12-16. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Gates County, NC: data center moratorium expires in 81 days
The documented term ends 2026-12-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Waterville Township, OH: data center moratorium expires in 81 days
The documented term ends 2026-12-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Orion Township, MI: data center moratorium expires in 81 days
The documented term ends 2026-12-17. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Jackson County, MO: data center moratorium expires in 83 days
The documented term ends 2026-12-19. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Cache County, UT: data center moratorium expires in 84 days
The documented term ends 2026-12-20. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Peosta, IA: data center moratorium expires in 84 days
The documented term ends 2026-12-20. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Clinton, TN: data center moratorium expires in 86 days
The documented term ends 2026-12-22. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Coweta County, GA: data center moratorium expires in 87 days
The documented term ends 2026-12-23. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Snohomish County, WA: data center moratorium expires in 88 days
The documented term ends 2026-12-24. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets. - Sedgwick County, KS: data center moratorium expires in 88 days
The documented term ends 2026-12-24. If your community wants it extended, that decision usually has to reach a meeting agenda weeks beforehand — check when the board next meets.
Changed in the last 7 days
5 status changes — pauses enacted, extended, lapsed or rescinded, plus 5 rows newly added to the tracker. Full week-by-week log · Subscribe by RSS
- Waterford Township, MI — Status changed Enacted → Expired
- Roswell, GA — Status changed Enacted → Expired
- Augusta, GA — Status changed Enacted → Expired
- Augusta-Richmond County, GA — Status changed Enacted → Expired
- Shawnee Township, OH — Shortened Now runs to 2027-10-13
What a moratorium looks like
The going rate, computed from the tracker. Useful when a council asks "how long do these usually run?" — the answer is in the record, not in the developer's talking points.
How long they run
336 local actions have both a start and a documented end date. Median term: 12 months. 12 have since been extended at least once.
A further 73 are standing bans with no end date and 8 run until a condition is met, usually adoption of new zoning rules.
Who passes them
Local actions by the kind of body that acted, from the locality name on the record.
Size thresholds
55 rows state a size trigger in their note — the point at which the pause applies. Most common: 10 MW (5), 100,000 sq ft (5), 10,000 sq ft (5), 20 MW (3), 50 MW (3). The rest cover every data center regardless of size, or pause a specific approval such as rezoning.
All tracked moratoriums
Status is what applies today: a moratorium with a documented end date flips to Expired on its own once that date passes. Rows marked Unverified have not been read against a primary source — treat them as a lead to check, not a fact to cite. Extensions are common, so an expiry date is the earliest a pause could have ended, not proof that it did. The table pages in 25 rows at a time — filter or search to narrow it, or Show all before printing or using Ctrl-F, since hidden rows are invisible to both.
| Locality | State | Level | Status | When | Note | Source |
|---|---|---|---|---|---|---|
| Denver | CO | Local | Enactedexpires 2027-05-21 | May 21, 2026 | 1 year or until updated data center regulations are adopted | SourceNews read 2026-08-04 |
| Baltimore City | MD | Local | Enactedexpires 2027-06-16 | Jun 16, 2026 | CB 26-0158: 1 year, facilities drawing 10 MW or more; 9-month impact study | SourceNews read 2026-08-04 |
| Reno | NV | Local | Enactedexpires 2027-08-31 | Extended Jun 1, 2026 | Extended 6-1 through Aug 2027 while permanent rules are drafted | SourceNews read 2026-08-04 |
| Dubuque County | IA | Local | Enactedexpires 2027-05-26 | May 26, 2026 | 12-month pause on permits and zoning requests for data center construction or expansion, passed 2-1 and amended up from 120 days after a unanimous Planning and Zoning Commission recommendation; county will host weekly work sessions and at least four public town halls | SourceNews read 2026-08-13 |
| Bloomington | IL | Local | Enactedexpires soon — 2026-11-26 | May 26, 2026 | 6-month pause, unanimous; facilities over 5 MW. At least two public hearings required during the moratorium period | SourceNews read 2026-08-13 |
| Iron County | UT | Local | Enactedexpires soon — 2026-11-22 | May 26, 2026 | Ordinance 2026-13: 180-day halt on data centers, data center power plants, and solar power plants; prospective only | SourceOfficial read 2026-08-13 |
| Sauk County | WI | County | Enactedfixed term, end date not recorded | Sep 15, 2026 | Ordinance 07-2026-0 amends the county zoning code to enact an 18-month moratorium on receipt of applications and the granting of all zoning permits or approvals for siting or placement of data centers. Effective on publication; runs 18 months from publication or until the board amends or rescinds it, whichever comes first. Publication date not recorded, so no end date is stored | SourceNews read 2026-09-20 |
| Sawyer County | WI | County | Enactedfixed term, end date not recorded | Aug 20, 2026 | County board adopted an 18-month temporary moratorium on development of large data centers and associated infrastructure, to give staff time to draft setback, permitting and performance standards. Zoning committee had recommended it 5-0 on Jul 15. Source is meeting coverage, not the county's own ordinance; end date is not stated in it | SourceNews read 2026-09-20 |
| Milwaukee | WI | Local | Proposedno fixed end — runs until a condition is met | Aug 10, 2026 | Proposed ordinance would bar city departments from accepting or processing applications to construct, enlarge, expand, convert or occupy data centers, for one year after passage or until the zoning code is amended to regulate them, whichever comes first. Zoning Code Technical Committee endorsed it Aug 10; City Plan Commission hearing set for Sep 28, 2026. Common Council approval still required — not yet adopted | SourceNews read 2026-09-20 |
| Manitowoc County | WI | Local | Enactedexpires 2027-10-29 | Apr 29, 2026 | 18-month pause, unanimous; covers facilities with more than 1 PB of storage. Requested by three towns (Two Creeks, Two Rivers, Mishicot) after land-purchase approaches to farmers | SourceNews read 2026-08-13 |
| Smithfield | RI | Local | Enactedno end date — permanent | Jun 4, 2026 | Adopted 4-1 May 5, effective Jun 4; data centers not permitted in any zoning district | SourceNews read 2026-08-04 |
| Meridian Township | MI | Local | Enactedexpires soon — 2026-11-19 | May 19, 2026 | 6-month pause on data centers and battery storage facilities; preemptive — no proposals pending | SourceNews read 2026-08-13 |
| Washington Township (Macomb Co.) | MI | Local | Enactedexpires soon — 2026-11-23 | May 2026 | 6-month pause or until zoning ordinance amendments take effect; passed after Prologis withdrew a 312-acre 'technical campus' application | SourceNews read 2026-08-13 |
| Hill County | TX | Local | Rescindedterm not documented | Rescinded Jun 4, 2026 | 1-year moratorium passed May 2026, rescinded after a $100M federal suit argued Texas counties lack moratorium authority; suit dismissed Jul 2026. Replaced with a disclosure checklist for large projects | SourceNews read 2026-08-04 |
| DeKalb County | GA | Local | Enactedexpires 2027-03-30 | Extended Jul 7, 2026 | Extended 6-1 through Mar 30, 2027 — two weeks after the commission rejected the planning department's proposed data center zoning rules, so the pause is now the only thing holding the line | SourceNews read 2026-08-04 |
| Lysander (Onondaga Co.) | NY | Local | Enactedexpires soon — 2026-11-06 | May 7, 2026 | 6-month; no applications accepted by Town, Planning or Zoning boards | SourceNews read 2026-08-04 |
| Perth (Fulton Co.) | NY | Local | Enactedexpires 2027-06-04 | Jun 4, 2026 | 1-year, passed 3-0; extendable by simple resolution | SourceNews read 2026-08-04 |
| Tonawanda (Erie Co.) | NY | Local | Enactedexpires 2027-08-03 | Effective Aug 3, 2026 | Local Law 2-2026: 1-year pause on facilities drawing 20 MW or more — a lower threshold than the state EO's 50 MW | SourceNews read 2026-08-04 |
| Newfield (Tompkins Co.) | NY | Local | Enactedexpires 2027-07-09 | Jul 9, 2026 | 1-year townwide pause on data processing centers and cryptocurrency mining; town is drafting comprehensive-plan amendments before it lapses | SourceNews read 2026-08-04 |
| Groton | CT | Local | Expiredterm ran to 2023-06-21 | Jun 21, 2022 | 1-year moratorium on data centers over 5,000 sq ft; lapsed into permanent zoning in Jun 2023 capping buildings at 12,500 sq ft and barring water cooling | SourceNews read 2026-08-04 |
| Peculiar | MO | Local | Enactedno end date — permanent | Oct 2024 | Board of Aldermen reversed an earlier zoning change and struck 'data center' from the light-industrial code, permanently blocking Diode Ventures' $1.5B Harper Road Technology Park. A 100-day moratorium (Aug 2024) preceded the permanent change | SourceNews read 2026-08-13 |
| Bangor | ME | Local | Enactedexpires soon — 2026-10-10 | Apr 13, 2026 | 180-day pause, 9-0. City cited lack of information about infrastructure impacts and no state-level framework to reference | SourceNews read 2026-08-13 |
| Gates County | NC | Local | Enactedexpires 2026-12-17 | Dec 17, 2025 | 1-year pause, unanimous; covers all data center and crypto mining applications. Preventative — prompted by two inquiries from a data center consulting firm. County water system has been under its own moratorium since 2018 | SourceOfficial read 2026-08-13 |
| Brevard | NC | Local | Expiredterm ran to 2026-06-23 | Mar 2026 | 90-day moratorium while city staff draft UDO text amendments. Term may have lapsed — confirm current status with the city | SourceNews read 2026-08-13 |
| Clay County | NC | Local | Enactedno end date — permanent | Jan 8, 2026 | Permanent ban — Ordinance No. 01.08.2026 prohibits the establishment, construction, expansion, or operation of commercial data centers in all zoning districts | SourceNews read 2026-08-13 |
As of August 2026 · changes weekly — re-check before citing
Illustrative rather than exhaustive — dozens of localities churn weekly, and this tracks the ones we have read a source for. **Each row carries its own provenance.** Rows showing a verification date link to the ordinance, the enacting body's own page, or a datable report of the vote, and were read on that date. Rows marked *unverified* came from bulk compilation and have not been checked against a primary source — the locality, the year, and the status may all be off. Verify one of those with the town clerk before citing it as precedent. **Expiry is derived, not asserted.** A row with a documented end date flips to *Expired* on its own once that date passes. A time-limited moratorium whose start date was never documented keeps showing as enacted — that is a known gap, not a claim that it is still in force. Moratoriums are also routinely extended, so an expiry date is the earliest it could have ended, not proof that it did.
See the full interactive map and filters in the GridWatch toolkit, or read how we count — what qualifies as a tracked action, and why our number differs from every other public tracker's.
Use this data
The whole tracker, with per-row sources, verification dates and derived expiry, as a documented download. Free to reuse with attribution (CC BY 4.0) — cite it, chart it, or load it into your own tracker. Subscribe to changes by RSS.
Schema — 26 fields
| Field | Meaning |
|---|---|
id | Stable row id, derived from locality + state — matches the community-page slug |
locality | Town, city or county taking the action; 'X (statewide)' for state-level |
state | USPS two-letter code |
level | Local or State |
status | As recorded: Enacted, Proposed, Rejected, Vetoed or Rescinded |
effective_status | Status today. Equals `status`, except an Enacted row past its `expires` date reads Expired. Use this one |
expired | true when a documented term has run out |
days_left | Days until `expires`; negative once past, null when no end date is recorded |
when | Human-readable date of the action, as reported |
date | ISO date parsed from `when`; a month- or year-only report keeps that precision rather than guessing a day |
date_precision | day, month, or year — how exact `date` is |
expires | ISO date the term lapses, or null when permanent, condition-based, or not documented |
term_kind | How the term is bounded: until_date (has an `expires`), standing (permanent ban or standing statute), until_event (ends on a condition), fixed_undated (a stated duration whose end date isn't recorded), unknown (not documented). Derived; `until_date` always wins over the stored `term` |
term_label | Plain-language rendering of `term_kind` |
note | Scope, threshold, vote count and other detail |
source | URL this row was read from, or null if unverified |
source_kind | official (the enacting body's own record: a .gov page, an ordinance host, an agenda/minutes system), roundup (one article covering several localities — the ordinance itself is still unfound), or news. Null when unsourced |
ordinance_url | Direct link to the ordinance or resolution text, when found separately from `source`. Null for most rows today — this is a known gap, not a claim nothing exists |
as_of | Date the source was read, or null |
verified | true when a source is recorded. false means nobody has checked this row — treat it as a lead |
threshold | Size that triggers the pause (MW, acres, or square footage), parsed from `note`. Null when `note` doesn't state one |
covers | What the row applies to, when the note says so unambiguously: new_applications, rezoning, permits, or all_uses. Null otherwise — not guessed |
events | Status history as a list of {date, kind, label, source}. Every row gets at least its own current action; a later extension, rescission, or replacement is a second entry, appended by hand as it's researched — not every row has more than one yet |
replaced_by | Locality of the ordinance that superseded this one, when this moratorium ended by being replaced rather than lapsing or being rescinded outright. Null for almost every row today — a known gap, tracked as it's researched |
lat | Latitude, null for state-level rows |
lon | Longitude, null for state-level rows |
Read effective_status,
not status: a moratorium whose documented term has run out
reads Expired there, and that is the field the page itself
renders. Rows with verified: false have no source on record —
they are leads to check, not facts to cite.
Embed the tracker on your own site
Self-contained and filterable by state. It updates when this page does, so you are not maintaining a copy.
<iframe src="https://aigridwatch.com/embed/moratoriums.html"
width="100%" height="560" style="border:0"
title="Data center moratorium tracker"></iframe>
<p>Data: <a href="https://aigridwatch.com/moratoriums">AI GridWatch
moratorium tracker</a> (CC BY 4.0)</p>
Please keep the attribution line under the widget — links inside an iframe don't credit the source, and the CC BY 4.0 license asks for attribution.
Missing one? Tell us
A vote we have not tracked, a term that was extended, a link that died. Every row here started as a document somebody read — send the document and it gets checked and added with a source and a date, usually within a week.
What happened next: case studies
Six communities that took action — what they won, what they lost, and what changed.
Groton, CT — A one-year pause turned into a permanent size cap
Groton's Planning and Zoning Commission adopted a one-year moratorium on data centers over 5,000 sq ft in June 2022 — and spent that year writing rules rather than letting it lapse. After a final public hearing in June 2023 the town adopted data center regulations, effective that July, capping data center buildings at 12,500 sq ft. Hyperscale campuses typically run 150,000–350,000 sq ft, so the cap excludes them by size instead of by argument. The moratorium was only the mechanism; the size cap is what holds.
Peculiar, MO — The town deleted 'data center' from its zoning code
Peculiar had already cleared the way for Diode Ventures' $1.5B Harper Road Technology Park by adding a 'data center' definition to its light-industrial zoning code. After hundreds of residents from Peculiar and neighbouring Raymore turned out against it, the Board of Aldermen voted unanimously in October 2024 to strike that definition back out — blocking the project without ever passing a moratorium. Removing a permitted use is a quieter tool than a ban, and here it was a faster one.
Cheyenne, WY — Council rejected a pause with a 3,200-acre expansion already moving
Microsoft announced a 3,200-acre expansion of its Cheyenne campus in April 2026, and Wyoming DEQ approved permits for 30 gas-fired engines plus emergency generators. On May 27, 2026 the city council voted 8–1 against a 12-month moratorium after three and a half hours of public comment — supporters raising water and noise, opponents raising jobs and tax base. The ratepayer question is being handled through Black Hills Energy's Large Power Contract Service tariff, under which Microsoft pays directly for the infrastructure it needs, rather than through anything the city negotiated. No community benefit agreement appears in the reporting.
Prince William County, VA — Voters removed the board chair; the courts voided the rezoning
In 2022 a board majority led by Chair Ann Wheeler rezoned more than 2,000 acres of farmland for the Prince William Digital Gateway. On June 20, 2023 Wheeler lost the Democratic primary to Deshundra Jefferson, who had campaigned against large-scale data centers. The board approved the rezoning 4–3 that December regardless — and it was the courts, not the ballot box, that ended it: the rezoning was voided on appeal and a developer withdrew, effectively killing the project. Statewide, Virginia voter support for new data centers fell from 69% in 2023 to 35%. Elections changed who was in the room; litigation changed the outcome.
The Dalles, OR — Google funded the water system — and its share of the water kept climbing
Under a 2021 agreement Google paid roughly $28.5M toward upgrades to The Dalles' water treatment and storage, including an aquifer storage and recovery system it later handed to the city, and bought and donated 3.88 million gallons/day of water rights from a closed aluminium smelter. What the deal did not include was a cap on Google's own draw. When The Oregonian sued for the usage records, the city spent 13 months fighting disclosure before settling — and the records showed the campus using about 29% of the city's water, rising to roughly 40% (some 550 million gallons a year) by 2025. Infrastructure money is not the same protection as a volume limit. This is the case that shows the difference, and the reason to put a cap in writing.
Mesa, AZ — Zoning rules instead of a moratorium: setbacks, height caps, sound study
With 15 data centers built, approved or proposed on roughly 1,500 acres in six years, Mesa's council introduced zoning controls 6–0 and adopted them in July 2025. Data centers are now allowed only where the council specifically authorises a Planned Area Development overlay on industrial land, and each must sit at least 400 feet from residential, stay under 60 feet tall, screen its mechanical equipment, and submit a sound study. Water cooling was argued in council — Councilwoman Jenn Duff pushed to restrict it during drought — but did not make it into the adopted rules. Worth reading as a list of what a council will grant without a moratorium, and what it won't.